19714 W LASSEN ST 91311

Certificate Information: 19714 W LASSEN ST 91311

Application / Permit
21010-20000-04151
Plan Check / Job No.
B21VN10817
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (40'-5"x21'-10"),732 SQFT ADU PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 3/22/2022
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 PETER MOSESIAN
Corrections Issued 9/18/2021 PETER MOSESIAN
Quality Review Completed 9/28/2021 OMID HEDAYAT
Building Plans Picked Up 9/30/2021 APPLICANT
Plan Check Approved 2/11/2022 PETER MOSESIAN
Issued 3/22/2022 APPLICANT
CofO in Progress 11/13/2025 DAVID SCANTLIN
Permit Finaled 11/13/2025 JOHN JANSON
CofO Issued 11/13/2025 JOHN JANSON
Permit Finaled 11/13/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/15/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/18/2021 CARLOS AGUILERA
Sewer availability Cleared 10/18/2021 CARLOS AGUILERA
ZA Case Cleared 10/19/2021 PABLO ESTRADA
Hydrant and Access approval Cleared 1/22/2022 GILBERT URREA
Low Impact Development Cleared 1/27/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 2/10/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/30/2022 Approved DAVID SCANTLIN
Footing/Foundation/Slab 3/31/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 5/27/2022 Partial Approval JEFFREY PARD
Rough-Elec/Plmb/HVAC 5/27/2022 Approved JEFFREY PARD
Insulation 6/6/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 6/6/2022 Approved JEFFREY PARD
Drywall Nailing 6/27/2022 Approved JEFFREY PARD
Green Building Rough 6/27/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 6/27/2022 Approved JEFFREY PARD
Shower Pan 6/27/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 10/5/2022 No Access for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 11/8/2022 Approved JOHN KIDWELL
Final 11/8/2022 Corrections Issued JOHN KIDWELL
Green Building Final 11/8/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 11/8/2022 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 11/8/2022 Approved JOHN KIDWELL
Final 11/18/2022 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/18/2022 SGSOV Not Ready DAVID SCANTLIN
Service/Power Release 11/18/2022 Not Ready for Inspection DAVID SCANTLIN
Final 3/10/2025 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Approved DAVID SCANTLIN
Service/Power Release 3/10/2025 Not Ready for Inspection DAVID SCANTLIN
Final 9/2/2025 No Access for Inspection KRISTEN CAUSEY
Service/Power Release 9/2/2025 No Access for Inspection KRISTEN CAUSEY
Final 9/11/2025 Not Ready for Inspection KRISTEN CAUSEY
Service/Power Release 9/11/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 11/14/2025 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 11/14/2025 Approved DAVID SCANTLIN