9752 N REMICK AVE 91331

Certificate Information: 9752 N REMICK AVE 91331

Application / Permit
21010-20000-04119
Plan Check / Job No.
B21VN10743
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (40'x 29') ONE-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC- 12,22 A.33 (c) and (d). WORK PER ENGINEER.
Permit Issued
Issued on 4/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 TROY DEGUZMAN
Corrections Issued 8/28/2021 TROY DEGUZMAN
Quality Review Completed 9/2/2021 OMID HEDAYAT
Building Plans Picked Up 9/16/2021 APPLICANT
Applicant returned to address corrections 1/21/2022 TROY DEGUZMAN
Plan Check Approved 1/24/2022 TROY DEGUZMAN
Issued 4/20/2022 APPLICANT
CofO in Progress 11/21/2022 MICHEL ABAJAN
Permit Finaled 11/30/2022 DANIEL ORRANTE
CofO Issued 11/30/2022 DANIEL ORRANTE
Permit Finaled 11/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/18/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/25/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 10/25/2021 JOSE DUARTE-DIAZ
Low Impact Development Cleared 1/18/2022 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 1/20/2022 JOSE DUARTE-DIAZ

Contact Information

Architect Battle,, Nathan Clarence; Lic. No.: C13768 969 W ALMOND STREET      COMPTON, CA 90220
Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/9/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 5/11/2022 Not Ready for Inspection MICHEL ABAJAN
METHANE-Barrier 5/11/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 5/11/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 5/12/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/6/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/6/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/6/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 6/6/2022 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 6/6/2022 Approved JENNIFER RABUCHIN
METHANE-Rough 6/6/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/6/2022 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 6/6/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/21/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/21/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Partial Inspection MICHEL ABAJAN
Green Building Rough 6/21/2022 Approved MICHEL ABAJAN
HVAC-Rough 6/21/2022 Approved MICHEL ABAJAN
METHANE-Rough 6/21/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 6/21/2022 Approved MICHEL ABAJAN
Insulation 7/5/2022 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 7/5/2022 Partial Approval ARAM AVEDISIAN
Drywall Nailing 7/12/2022 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 8/23/2022 Corrections Issued DEANDRE HOFFMAN
Underground Mechanical 8/25/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/12/2022 Approved MICHEL ABAJAN
Final 10/12/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 10/12/2022 Approved MICHEL ABAJAN
HVAC-Final 10/12/2022 Approved MICHEL ABAJAN
MERV13>=Final 10/12/2022 Approved MICHEL ABAJAN
PLUMBING-Final 10/12/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/12/2022 SGSOV Approved MICHEL ABAJAN
Service/Power Release 10/12/2022 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 10/12/2022 Approved MICHEL ABAJAN
Final 11/1/2022 Not Ready for Inspection CALEB MEISTER
Service/Power Release 11/1/2022 Conditional Approval CALEB MEISTER
Final 11/21/2022 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 11/21/2022 Approved MICHEL ABAJAN