6611 N PEACH AVE 91406
Certificate Information: 6611 N PEACH AVE 91406
- Application / Permit
- 21010-20000-04095
- Plan Check / Job No.
- B21VN10654
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN - Proposed Detached ADU per ordinance.
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2021 | MICHAEL LOPEZ |
| Corrections Issued | 8/10/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 1/23/2022 | MICHAEL LOPEZ |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 8/13/2025 | RYAN SALAZAR |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/17/2021 | DAGOVERTO GUERRERO |
| ZI | Cleared | 8/17/2021 | PABLO ESTRADA |
| Construction near power lines | Cleared | 10/19/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/19/2021 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 10/28/2021 | LONDY ALVARADO |
| Hydrant and Access approval | Cleared | 11/5/2021 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 1/3/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/18/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 8/5/2022 | Approved | RICHARD DOCKUS |
| Sewer | 8/19/2022 | Partial Approval | RICHARD DOCKUS |
| Sewer | 8/24/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/4/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/4/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/4/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 5/4/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 5/4/2023 | Approved | RYAN SALAZAR |
| Insulation | 6/7/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/7/2023 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 6/7/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/16/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/16/2023 | Approved | RYAN SALAZAR |
| Final | 11/8/2024 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 11/8/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 11/8/2024 | Approved | RYAN SALAZAR |
| Final | 4/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Service/Power Release | 4/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 8/14/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 8/14/2025 | Approved | RYAN SALAZAR |