8416 N NESTLE AVE 91325
Certificate Information: 8416 N NESTLE AVE 91325
- Application / Permit
- 21010-20000-04091
- Plan Check / Job No.
- B21VN10642
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1 STORY (37'-3"x35'-6"),1136 SQFT ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | PETER MOSESIAN |
| Corrections Issued | 9/19/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/28/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/30/2021 | APPLICANT |
| Plan Check Approved | 7/19/2022 | PETER MOSESIAN |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 8/18/2023 | DAVID SCANTLIN |
| Permit Finaled | 8/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/18/2023 | DANIEL ORRANTE |
| CofO Issued | 8/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 3/14/2022 | DANG NGUYEN |
| Address approval | Cleared | 3/18/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 3/29/2022 | CHRIS CHAHBAZ |
| Hydrant and Access approval | Cleared | 4/30/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 6/8/2022 | SUNG JOON WON |
| Construction near power lines | Cleared | 6/15/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 7/6/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/11/2022 | Partial Approval | JEFFREY PARD |
| Underground Mechanical | 8/11/2022 | Not Ready for Inspection | JEFFREY PARD |
| Footing/Foundation/Slab | 8/17/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 10/5/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/5/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/18/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 10/18/2022 | Partial Approval | JOHN KIDWELL |
| Insulation | 11/18/2022 | Conditional Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 12/5/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 12/5/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 12/5/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 12/5/2022 | Approved | DAVID SANDOVAL |
| Pre-Inspection | 12/5/2022 | Partial Inspection | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 12/5/2022 | Approved | DAVID SANDOVAL |
| Shower Pan | 1/30/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 2/16/2023 | Approved | DAVID SCANTLIN |
| Final | 8/14/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 8/14/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 8/14/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 8/14/2023 | Approved | DAVID SCANTLIN |
| Final | 8/17/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 8/17/2023 | Approved | JOHN KIDWELL |
| Service/Power Release | 8/17/2023 | Approved | JOHN KIDWELL |
| Final | 8/18/2023 | OK to Issue CofO | DAVID SCANTLIN |