4948 N RUBIO AVE 91436
Certificate Information: 4948 N RUBIO AVE 91436
- Application / Permit
- 21010-20000-04079
- Plan Check / Job No.
- B21VN10600
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 52' X 16' ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 12/27/2021
- Issuing Office
- Current Status
- CofO Issued on 12/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | SELLA BENYAMIN |
| Corrections Issued | 8/31/2021 | SELLA BENYAMIN |
| Quality Review Completed | 9/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| Plan Check Approved | 12/23/2021 | SELLA BENYAMIN |
| Issued | 12/27/2021 | APPLICANT |
| CofO in Progress | 12/15/2022 | VINCENT HANLEY |
| Permit Finaled | 12/23/2022 | MICHAEL SMITH |
| CofO Issued | 12/23/2022 | MICHAEL SMITH |
| Permit Finaled | 12/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/13/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/22/2021 | KHAING AYE |
| Hydrant and Access approval | Cleared | 12/9/2021 | GREGORY HOERNER |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 2/3/2022 | Partial Approval | DAVID SANDOVAL |
| Underground Mechanical | 2/3/2022 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 2/9/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | DAVID SANDOVAL |
| HVAC-Rough | 3/31/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 3/31/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 4/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 4/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 4/15/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 4/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/29/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 4/29/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 4/29/2022 | Partial Approval | DAVID SANDOVAL |
| Shower Pan | 4/29/2022 | Approved | DAVID SANDOVAL |
| Insulation | 5/5/2022 | Corrections Issued | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 5/5/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 5/13/2022 | Approved | PETER FOLLING |
| Insulation | 5/13/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 5/13/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 11/15/2022 | Approved | VINCENT HANLEY |
| Gas Test | 11/15/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 11/15/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 11/15/2022 | Approved | VINCENT HANLEY |
| Service/Power Release | 11/15/2022 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | VINCENT HANLEY |
| Final | 12/14/2022 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 12/14/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 12/14/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 12/14/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 12/14/2022 | Approved | VINCENT HANLEY |
| Smoke Detectors | 12/14/2022 | Approved | VINCENT HANLEY |