4948 N RUBIO AVE 91436

Certificate Information: 4948 N RUBIO AVE 91436

Application / Permit
21010-20000-04079
Plan Check / Job No.
B21VN10600
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 52' X 16' ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 12/27/2021
Issuing Office
Current Status
CofO Issued on 12/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 SELLA BENYAMIN
Corrections Issued 8/31/2021 SELLA BENYAMIN
Quality Review Completed 9/2/2021 STEVEN KIM
Building Plans Picked Up 9/3/2021 APPLICANT
Plan Check Approved 12/23/2021 SELLA BENYAMIN
Issued 12/27/2021 APPLICANT
CofO in Progress 12/15/2022 VINCENT HANLEY
Permit Finaled 12/23/2022 MICHAEL SMITH
CofO Issued 12/23/2022 MICHAEL SMITH
Permit Finaled 12/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/10/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/13/2021 GABRIEL ROBLES
Sewer availability Cleared 9/13/2021 GABRIEL ROBLES
Low Impact Development Cleared 11/22/2021 KHAING AYE
Hydrant and Access approval Cleared 12/9/2021 GREGORY HOERNER
Roof/Waste drainage to street Cleared 12/9/2021 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/3/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 2/3/2022 Partial Approval DAVID SANDOVAL
Underground Mechanical 2/3/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 2/9/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Partial Approval DAVID SANDOVAL
HVAC-Rough 3/31/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 3/31/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 4/15/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 4/15/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 4/15/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 4/15/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 4/15/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 4/15/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 4/29/2022 Approved DAVID SANDOVAL
HVAC-Rough 4/29/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 4/29/2022 Partial Approval DAVID SANDOVAL
Shower Pan 4/29/2022 Approved DAVID SANDOVAL
Insulation 5/5/2022 Corrections Issued DAVID SANDOVAL
Verify Sprinkler Sign Off 5/5/2022 Approved DAVID SANDOVAL
Drywall Nailing 5/13/2022 Approved PETER FOLLING
Insulation 5/13/2022 Approved PETER FOLLING
Interior/Exterior Lathing 5/13/2022 Approved PETER FOLLING
ELECTRICAL-Final 11/15/2022 Approved VINCENT HANLEY
Gas Test 11/15/2022 Approved VINCENT HANLEY
HVAC-Final 11/15/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Final 11/15/2022 Approved VINCENT HANLEY
Service/Power Release 11/15/2022 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 12/14/2022 Approved VINCENT HANLEY
Final 12/14/2022 OK to Issue CofO VINCENT HANLEY
Green Building Final 12/14/2022 Approved VINCENT HANLEY
Green Building Rough 12/14/2022 Approved VINCENT HANLEY
HVAC-Final 12/14/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/14/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 12/14/2022 Approved VINCENT HANLEY
Smoke Detectors 12/14/2022 Approved VINCENT HANLEY