5511 1/2 N COLFAX AVE 91606

Certificate Information: 5511 1/2 N COLFAX AVE 91606

Application / Permit
21010-20000-04073
Plan Check / Job No.
B21VN10582
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. New Accessory Dwelling Unit y Installing a RADCO Approved Factory Built Housing Unit over a raised floor foundations. FBH Per: RAD-31-1027 & RAD-31-1028. ADU PER GCS 65852.2(e)(1)(D)
Permit Issued
Issued on 4/1/2022
Issuing Office
Current Status
CofO Issued on 4/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2021 APPLICANT
Assigned to Plan Check Engineer 8/11/2021 MONICA RAMIREZ
Corrections Issued 8/12/2021 MONICA RAMIREZ
Applicant returned to address corrections 1/7/2022 MONICA RAMIREZ
Applicant returned to address corrections 1/31/2022 MONICA RAMIREZ
Applicant returned to address corrections 2/7/2022 MONICA RAMIREZ
Applicant returned to address corrections 2/10/2022 MONICA RAMIREZ
Plan Check Approved 3/24/2022 MONICA RAMIREZ
Issued 4/1/2022 APPLICANT
CofO in Progress 4/25/2023 JACK KARGODORIAN
Permit Finaled 4/27/2023 MICHAEL SMITH
CofO Issued 4/27/2023 MICHAEL SMITH
Permit Finaled 4/27/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/24/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/28/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/28/2021 DAGOVERTO GUERRERO
Tenant Habitability Plan Cleared 1/7/2022 PHILLIP MUNGUIA
Specific Plan Cleared 2/8/2022 ERIN NASH
Low Impact Development Cleared 3/16/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 3/18/2022 DAGOVERTO GUERRERO

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B       ,
Engineer Sveiven,, Shane; Lic. No.: C89133 1909 S ALMA STREET      SAN PEDRO, CA 90731
Engineer Tompos,, Eric Joseph; Lic. No.: C70218 7690 W NOTTINGHAM DR      NAPPANEE, IN 46550

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/11/2022 Not Ready for Inspection DAVID MATSON
Sewer 5/9/2022 Partial Approval NATHAN BUCK
Underground Mechanical 5/9/2022 Partial Approval NATHAN BUCK
Excavation/Setback/Form/Re-Bar 8/1/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 9/1/2022 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 4/7/2023 Approved JACK KARGODORIAN
Final 4/7/2023 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 4/7/2023 Approved JACK KARGODORIAN
Green Building Final 4/7/2023 Approved JACK KARGODORIAN
Green Building Rough 4/7/2023 Approved JACK KARGODORIAN
MERV13>=Final 4/7/2023 Approved JACK KARGODORIAN
MERV13>=Rough 4/7/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Not Required JACK KARGODORIAN
Service/Power Release 4/7/2023 Approved JACK KARGODORIAN
Smoke Detectors 4/7/2023 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 4/7/2023 Approved JACK KARGODORIAN
Final 4/25/2023 OK to Issue CofO JACK KARGODORIAN