5909 N SHIRLEY AVE 91356
Certificate Information: 5909 N SHIRLEY AVE 91356
- Application / Permit
- 21010-20000-04059
- Plan Check / Job No.
- B21VN10572
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 29'-3" X 48'-1" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 1/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 9/21/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/1/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 2/27/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/1/2022 | APPLICANT |
| Issued | 3/9/2022 | APPLICANT |
| CofO in Progress | 6/23/2023 | JON MCHUGH |
| Permit Finaled | 1/18/2024 | JOHN JANSON |
| CofO Issued | 1/18/2024 | JOHN JANSON |
| Permit Finaled | 1/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| ZA Case | Cleared | 9/29/2021 | DANG NGUYEN |
| Address approval | Cleared | 9/30/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/30/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 12/20/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/20/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 1/3/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/13/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 5/25/2022 | Approved | SEAN HAUPT |
| Service/Power Release | 7/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| Sewer | 7/29/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 7/29/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Approved | SEAN HAUPT |
| Wood Frame | 8/22/2022 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Wood Construction | 9/6/2022 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/13/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 9/13/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 9/13/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 9/13/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 9/13/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 9/13/2022 | Approved | SEAN HAUPT |
| Wood Frame | 9/13/2022 | Approved | SEAN HAUPT |
| Insulation | 10/4/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 10/4/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 10/13/2022 | Not Ready for Inspection | SEAN HAUPT |
| Drywall Nailing | 10/20/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/2/2022 | Approved | SEAN WIRCH |
| Final | 12/16/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/16/2022 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 12/16/2022 | Approved | SEAN HAUPT |
| Smoke Detectors | 12/16/2022 | Approved | SEAN HAUPT |
| Final | 5/24/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 5/24/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 6/23/2023 | Approved | JON MCHUGH |
| Final | 6/23/2023 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 6/23/2023 | Approved | JON MCHUGH |
| HVAC-Final | 6/23/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 6/23/2023 | Approved | JON MCHUGH |