9638 N WHITE OAK AVE 91325
Certificate Information: 9638 N WHITE OAK AVE 91325
- Application / Permit
- 21010-20000-04055
- Plan Check / Job No.
- B21VN10541
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 41'-4" X 60'-0" 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d) WITH ATTACHED COVERED PATIO. NFPA13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| Submitted | 8/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | COLIN LOREDO |
| Corrections Issued | 9/13/2021 | COLIN LOREDO |
| Quality Review Completed | 9/21/2021 | OMID HEDAYAT |
| Plan Check Approved | 2/8/2022 | COLIN LOREDO |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 4/29/2024 | JAVIER RAMOS JR |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
| CofO Issued | 5/1/2024 | RUBEN SALAS |
| Permit Finaled | 5/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/24/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 9/29/2021 | BRIAN MILLER |
| Low Impact Development | Cleared | 1/18/2022 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 1/25/2022 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 1/25/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/1/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/14/2022 | Corrections Issued | DEANDRE HOFFMAN |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 10/21/2022 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/9/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/27/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/10/2023 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 7/10/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 7/10/2023 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 7/10/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/14/2023 | Conditional Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/8/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/8/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/8/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/8/2023 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/29/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/29/2023 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 9/29/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 10/13/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 10/13/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 11/17/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/17/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 11/17/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 3/8/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 3/8/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/15/2024 | Approved | JAVIER RAMOS JR |
| Final | 4/15/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/15/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/15/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/15/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/15/2024 | Approved | JAVIER RAMOS JR |
| Final | 4/29/2024 | OK to Issue CofO | JAVIER RAMOS JR |