10052 W HILLGROVE DR 90210

Certificate Information: 10052 W HILLGROVE DR 90210

Application / Permit
21010-20000-04053
Plan Check / Job No.
B21VN10529
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 78'-0" x 52'-10" IRREGULAR SHAPED TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND TRELLIS. " NFPA 13-D FIRE SPRINKLERS THRU-OUT ". SEE COMMENTS.
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 SARKIS HARABEDIAN
Corrections Issued 9/7/2021 SARKIS HARABEDIAN
Quality Review Completed 9/8/2021 STEVEN KIM
Applicant returned to address corrections 12/1/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 1/14/2022 SARKIS HARABEDIAN
Plan Check Approved 1/24/2022 SARKIS HARABEDIAN
Issued 2/8/2022 APPLICANT
Building Plans Picked Up 2/8/2022 APPLICANT
CofO in Progress 8/15/2023 STEPHANIE SWANSON
No Progress 8/22/2023 MICHAEL PELHAM
CofO in Progress 8/23/2023 DANIEL ORRANTE
Permit Finaled 8/23/2023 DANIEL ORRANTE
CofO Issued 8/23/2023 DANIEL ORRANTE
Permit Finaled 8/23/2023 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 9/6/2021 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 9/6/2021 SARKIS HARABEDIAN
Address approval Cleared 9/14/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 9/14/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 9/14/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 9/14/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 9/14/2021 SAUL GARCIA
BHO/Hillside ordinance Cleared 9/14/2021 SAUL GARCIA
Permit Cleared 9/14/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 9/15/2021 SAUL GARCIA
Sewer availability Cleared 9/15/2021 SAUL GARCIA
Low Impact Development Cleared 10/29/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 10/29/2021 SAUL GARCIA
Hydrant and Access approval Cleared 11/16/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Koester,, Ronald Norman; Lic. No.: L5930 1815 SHADOW CANYON RD      ACTON, CA 93510
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/16/2022 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/2/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/10/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/10/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 5/11/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/11/2022 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 5/12/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 5/13/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 5/17/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/9/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 6/9/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/29/2022 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 6/29/2022 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 6/29/2022 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 6/29/2022 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 7/1/2022 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 7/19/2022 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 8/4/2022 Conditional Approval CHRISTOPHER WILSON
HVAC-Rough 9/7/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/7/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 9/9/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 9/12/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 9/12/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/12/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 9/13/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 9/29/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 9/29/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 9/29/2022 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 9/29/2022 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 9/30/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 9/30/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 9/30/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Shower Pan 9/30/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 9/30/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 10/3/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 10/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 10/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 10/13/2022 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 10/13/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 10/24/2022 Partial Approval STEPHANIE SWANSON
Drywall Nailing 11/2/2022 Approved ANDREW NAVE
Gas Test 11/2/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 11/2/2022 Approved ANDREW NAVE
PLUMBING-Final 6/29/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 6/30/2023 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 6/30/2023 Corrections Issued BRENDAN LOONEY
Final 6/30/2023 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 6/30/2023 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 6/30/2023 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 6/30/2023 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 6/30/2023 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 7/6/2023 Approved BRENDAN LOONEY
HVAC-Final 7/6/2023 Corrections Issued BRENDAN LOONEY
HVAC-Final 7/20/2023 Approved BRENDAN LOONEY
Service/Power Release 7/27/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 8/9/2023 Approved STEPHANIE SWANSON
Final 8/9/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 8/9/2023 Approved STEPHANIE SWANSON
Green Building Final 8/9/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 8/9/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 8/9/2023 Approved STEPHANIE SWANSON
Final 8/15/2023 OK to Issue CofO STEPHANIE SWANSON
Special/Order Compliance 8/22/2023 Corrections Issued MICHAEL PELHAM