20180 W MARLOW LANE 91326

Certificate Information: 20180 W MARLOW LANE 91326

Application / Permit
21010-20000-04011
Plan Check / Job No.
B21VN10384
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH ATTACHED THREE CAR GARAGE_STANDARD PLAN#653_ PLAN 2B_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 10/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 DAWN MC NULTY
Corrections Issued 9/15/2021 DAWN MC NULTY
Quality Review Completed 9/20/2021 STEVEN KIM
Building Plans Picked Up 10/1/2021 APPLICANT
Plan Check Approved 10/24/2022 DAWN MC NULTY
Issued 10/27/2022 APPLICANT
CofO in Progress 8/9/2023 HENRY KIM
Permit Finaled 8/10/2023 JOHN JANSON
CofO Issued 8/10/2023 JOHN JANSON
Permit Finaled 8/10/2023 JOHN JANSON

Permit Application Clearance Information

"T" removal Cleared 1/19/2022 LAUREN PADICK
CPC Cleared 1/19/2022 LAUREN PADICK
Frnt yard landscape/Water mgmt Cleared 1/19/2022 LAUREN PADICK
Miscellaneous Cleared 1/19/2022 LAUREN PADICK
Miscellaneous Cleared 1/19/2022 LAUREN PADICK
Miscellaneous Cleared 1/19/2022 LAUREN PADICK
Private street Cleared 1/19/2022 LAUREN PADICK
Specific Plan Cleared 1/19/2022 LAUREN PADICK
Tract Map conditions Cleared 1/19/2022 LAUREN PADICK
ZA Case Cleared 1/19/2022 LAUREN PADICK
ZA Case Cleared 1/19/2022 LAUREN PADICK
Address approval Cleared 1/24/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/24/2022 LEE GUILBEAUX
Permit Cleared 1/24/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/24/2022 DAWN MC NULTY
Roof/Waste drainage to street Cleared 1/24/2022 LEE GUILBEAUX
Sewer availability Cleared 1/24/2022 LEE GUILBEAUX
Low Impact Development Cleared 1/27/2022 AMMAR ELTAWIL
Hydrant and Access approval Cleared 5/20/2022 KURT CORRAL
GPI Written Notices Cleared 10/24/2022 DAWN MC NULTY
Grading Pre-Inspection Cleared 10/24/2022 DAWN MC NULTY

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN-TAGERT/LEGAL    HOSHAM, PA 19044
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Van, Gaale, Mark Allan; Lic. No.: C58680 185 W ORANGEWOOD AVE SUITE 200      ORANGE, CA 92868

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/24/2023 Partial Approval HENRY KIM
Footing/Foundation/Slab 2/10/2023 Corrections Issued HENRY KIM
Deputy Reinf. Concrete 2/14/2023 Conditional Approval HENRY KIM
Footing/Foundation/Slab 2/14/2023 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Corrections Issued HENRY KIM
Deputy Other (see comments) 4/3/2023 Conditional Approval HENRY KIM
Underground Mechanical 4/4/2023 Approved HENRY KIM
Deputy Drilled-In Anchors 4/5/2023 Conditional Approval HENRY KIM
Deputy Drilled-In Anchors 4/5/2023 Conditional Approval JUSTIN HAWLEY
Deputy Wood Construction 4/7/2023 Conditional Approval HENRY KIM
Sewer 4/7/2023 Approved HENRY KIM
Special/Order Compliance 4/7/2023 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval HENRY KIM
Deputy Wood Construction 4/14/2023 Conditional Approval HENRY KIM
ELECTRICAL-Rough 4/14/2023 Corrections Issued HENRY KIM
HVAC-Rough 4/14/2023 Approved HENRY KIM
PLUMBING-Rough 4/14/2023 Corrections Issued HENRY KIM
Special/Order Compliance 4/14/2023 Approved HENRY KIM
BUILDING-Rough-Frame 4/17/2023 Not Ready for Inspection HENRY KIM
Green Building Rough 4/17/2023 Approved HENRY KIM
Special/Order Compliance 4/17/2023 Approved HENRY KIM
Verify Sprinkler Sign Off 4/17/2023 Approved HENRY KIM
BUILDING-Rough-Frame 4/18/2023 Approved JEFFREY PARD
ELECTRICAL-Rough 4/18/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 4/18/2023 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 4/18/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 4/19/2023 Partial Approval HENRY KIM
Drywall Nailing 4/27/2023 Approved HENRY KIM
Interior/Exterior Lathing 4/27/2023 Approved HENRY KIM
Gas Test 5/22/2023 Approved HENRY KIM
Service/Power Release 6/14/2023 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/20/2023 SGSOV Approved HENRY KIM
ELECTRICAL-Final 8/8/2023 Approved HENRY KIM
Final 8/8/2023 OK to Issue CofO HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Approved HENRY KIM
Green Building Final 8/8/2023 Approved HENRY KIM
HVAC-Final 8/8/2023 Approved HENRY KIM
PLUMBING-Final 8/8/2023 Approved HENRY KIM
Smoke Detectors 8/8/2023 Approved HENRY KIM