12822 W MILBANK ST 91604
Certificate Information: 12822 W MILBANK ST 91604
- Application / Permit
- 21010-20000-03958
- Plan Check / Job No.
- B21VN10266
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED (30'-0"x40'-0")1200 SQFT ADU WITH A (30'-0"x40'-0") 1200 SQFT BASEMENT W/NFPA 13R THROUGHOUT PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- Valley
- Current Status
- Issued on 10/20/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | PETER MOSESIAN |
| Corrections Issued | 9/4/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/16/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| Plan Check Approved | 10/7/2022 | PETER MOSESIAN |
| Issued | 10/20/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2021 | LEE GUILBEAUX |
| ZI | Cleared | 12/8/2021 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 7/14/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/15/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/27/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 8/26/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/1/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Grading | 11/27/2023 | Corrections Issued | DAVID MATSON |
| Deputy Grading | 11/28/2023 | Conditional Approval | JUAN VALENZUELA |
| Deputy Grading | 11/30/2023 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 1/12/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 1/12/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 1/18/2024 | Conditional Approval | JOHN COLEMAN |
| Deputy Reinf. Concrete | 1/22/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/6/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/14/2024 | Partial Approval | JOHN COLEMAN |
| Reinforced Concrete Frame | 3/14/2024 | Partial Approval | JOHN COLEMAN |
| Deputy Reinf. Concrete | 3/18/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/23/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/24/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 4/26/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/3/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 5/7/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/15/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/29/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/31/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/31/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 5/31/2024 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 6/3/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 10/1/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 10/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/1/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 10/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 10/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 10/29/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/4/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 11/4/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 11/15/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/9/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/13/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |