6838 N JELLICO AVE 91406
Certificate Information: 6838 N JELLICO AVE 91406
- Application / Permit
- 21010-20000-03954
- Plan Check / Job No.
- B21VN10258
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-4" X 44'-1" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Current Status
- CofO Issued on 5/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/7/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 9/14/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/16/2021 | APPLICANT |
| Applicant returned to address corrections | 6/10/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 6/23/2022 | RAPHAEL ROSAS |
| Issued | 6/23/2022 | APPLICANT |
| CofO in Progress | 5/22/2023 | JON MCHUGH |
| Permit Finaled | 5/23/2023 | JOHN JANSON |
| CofO Issued | 5/23/2023 | JOHN JANSON |
| Permit Finaled | 5/23/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/27/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/27/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 1/14/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 4/20/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 4/27/2022 | ABDULLAH SADOZAI |
| Hydrant and Access approval | Cleared | 5/12/2022 | LAURINDA MEADE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/13/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 10/13/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 10/13/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/17/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 10/17/2022 | Partial Approval | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 10/17/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 10/24/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 11/1/2022 | Partial Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 11/28/2022 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 11/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 11/28/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/22/2022 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 12/22/2022 | Approved | JON MCHUGH |
| Green Building Rough | 12/22/2022 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 12/22/2022 | Approved | JON MCHUGH |
| Wood Frame | 12/22/2022 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 1/25/2023 | Approved | SEAN HAUPT |
| Insulation | 1/25/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/25/2023 | Approved | SEAN HAUPT |
| Shower Pan | 1/25/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 1/31/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 1/31/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/31/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 1/31/2023 | Corrections Issued | SEAN HAUPT |
| Final | 3/14/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 3/14/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 3/14/2023 | Corrections Issued | JON MCHUGH |
| Smoke Detectors | 3/14/2023 | Approved | JON MCHUGH |
| Final | 3/21/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 3/21/2023 | Approved | JON MCHUGH |
| Service/Power Release | 3/21/2023 | Approved | JON MCHUGH |
| Final | 5/22/2023 | Partial Approval | JON MCHUGH |