13089 W DEL SUR ST 91340

Certificate Information: 13089 W DEL SUR ST 91340

Application / Permit
21010-20000-03943
Plan Check / Job No.
B21VN10236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22' X 23'-5" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 1/24/2022
Issuing Office
Current Status
CofO Issued on 3/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/11/2021 RAPHAEL ROSAS
Corrections Issued 8/12/2021 RAPHAEL ROSAS
Plan Check Approved 12/27/2021 RAPHAEL ROSAS
Building Plans Picked Up 12/28/2021 APPLICANT
Issued 1/24/2022 APPLICANT
CofO in Progress 3/24/2023 MICHEL ABAJAN
Permit Finaled 3/28/2023 MICHAEL SMITH
CofO Issued 3/28/2023 MICHAEL SMITH
Permit Finaled 3/28/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/17/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/18/2021 CARLOS AGUILERA
Sewer availability Cleared 8/18/2021 CARLOS AGUILERA
Low Impact Development Cleared 10/29/2021 KHAING AYE
Roof/Waste drainage to street Cleared 11/1/2021 ABDULLAH SADOZAI
Construction near power lines Cleared 12/10/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 12/10/2021 MATTHEW CRAIG

Contact Information

Contractor D H Property Maintenance Inc; Lic. No.: 985811-B 11312 COVELLO STREET      SUN VALLEY, CA 91352

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/23/2022 Partial Approval DAVID MATSON
Underground Mechanical 2/23/2022 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 3/1/2022 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 3/7/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/15/2022 Not Ready for Inspection MICHEL ABAJAN
Deputy Reinf. Concrete 3/22/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 3/24/2022 Approved MICHEL ABAJAN
Underground Mechanical 3/24/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 6/3/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 6/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/7/2022 Corrections Issued JOHN HAYES
HVAC-Rough 6/7/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/7/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/28/2022 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 6/28/2022 Partial Approval ROBERT GOLD
PLUMBING-Rough 6/28/2022 Approved ROBERT GOLD
Shower Pan 6/28/2022 Approved ROBERT GOLD
Insulation 7/14/2022 Approved MICHEL ABAJAN
Drywall Nailing 7/27/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 7/27/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/27/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/20/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Not Ready MICHEL ABAJAN
Verify Sprinkler Sign Off 3/20/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/24/2023 Approved MICHEL ABAJAN
Final 3/24/2023 OK to Issue CofO MICHEL ABAJAN
Green Building Final 3/24/2023 Approved MICHEL ABAJAN
HVAC-Final 3/24/2023 Approved MICHEL ABAJAN
PLUMBING-Final 3/24/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 3/24/2023 Approved MICHEL ABAJAN
Smoke Detectors 3/24/2023 Approved MICHEL ABAJAN