7031 N CALHOUN AVE 91405
Certificate Information: 7031 N CALHOUN AVE 91405
- Application / Permit
- 21010-20000-03939
- Plan Check / Job No.
- B21VN10201
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2021 | KEVIN MORALES |
| Corrections Issued | 8/4/2021 | KEVIN MORALES |
| Plan Check Approved | 5/6/2022 | KEVIN MORALES |
| Issued | 1/27/2023 | APPLICANT |
| CofO in Progress | 2/20/2025 | RYAN SALAZAR |
| CofO in Progress | 2/20/2025 | RYAN SALAZAR |
| CofO in Progress | 4/15/2025 | RYAN SALAZAR |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
| CofO Issued | 4/17/2025 | RUBEN SALAS |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/8/2021 | RIDWAN HARDY |
| Address approval | Cleared | 3/10/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/10/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 4/27/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/28/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/23/2024 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 7/23/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 7/31/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/31/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Partial Approval | RYAN SALAZAR |
| Deputy Wood Construction | 9/25/2024 | Conditional Approval | ROBERT GOLD |
| HVAC-Rough | 10/7/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/7/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 10/15/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 10/15/2024 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 10/15/2024 | Approved | RYAN SALAZAR |
| Wood Frame | 10/15/2024 | Approved | RYAN SALAZAR |
| Insulation | 10/23/2024 | Approved | RYAN SALAZAR |
| Sewer | 10/23/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/28/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 11/5/2024 | Approved | RYAN SALAZAR |
| Sewer | 11/21/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 11/22/2024 | Approved | RYAN SALAZAR |
| Gas Test | 12/2/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 12/2/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 12/2/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/10/2024 | Approved | RYAN SALAZAR |
| Final | 1/31/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 1/31/2025 | Approved | RYAN SALAZAR |
| Pre-Inspection | 1/31/2025 | Partial Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 1/31/2025 | Approved | RYAN SALAZAR |
| Final | 2/20/2025 | Partial Approval | RYAN SALAZAR |
| Service/Power Release | 2/20/2025 | Approved | RYAN SALAZAR |
| Final | 4/16/2025 | OK to Issue CofO | RYAN SALAZAR |