1122 W 49TH ST 90037

Certificate Information: 1122 W 49TH ST 90037

Application / Permit
21010-20000-03930
Plan Check / Job No.
B21VN10176
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of an (E) detached garage into an ADU per ordinance 186,481.
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2021 APPLICANT
Assigned to Plan Check Engineer 8/3/2021 HELEN NGUYEN
Corrections Issued 8/3/2021 HELEN NGUYEN
Applicant returned to address corrections 10/18/2021 HELEN NGUYEN
Applicant returned to address corrections 10/27/2021 HELEN NGUYEN
Plan Check Approved 11/3/2021 HELEN NGUYEN
Issued 11/8/2021 APPLICANT
CofO in Progress 12/16/2022 SABAS ALONSO
Permit Finaled 2/4/2023 DEROLD HAUFF
CofO Issued 2/4/2023 DEROLD HAUFF
Permit Finaled 2/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/8/2021 THOMAS LANG
Address approval Cleared 9/10/2021 THOMAS LANG
Sewer availability Cleared 9/10/2021 THOMAS LANG
Construction near power lines Cleared 10/13/2021 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 10/18/2021 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/21/2022 Partial Approval SABAS ALONSO
PLUMBING-Rough 4/13/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Sewer 4/13/2022 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 4/13/2022 Partial Approval JOAQUIN GREENOUGH
Pre-Inspection 4/28/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 5/10/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 5/16/2022 Partial Approval SABAS ALONSO
PLUMBING-Rough 5/24/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 5/24/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 5/27/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 6/16/2022 Approved SABAS ALONSO
HVAC-Rough 6/16/2022 Approved SABAS ALONSO
PLUMBING-Rough 6/16/2022 Approved SABAS ALONSO
Wood Frame 6/16/2022 Not Ready for Inspection SABAS ALONSO
Wood Frame 6/17/2022 Corrections Issued SABAS ALONSO
Insulation 7/1/2022 Approved SABAS ALONSO
Drywall Nailing 7/6/2022 Approved SABAS ALONSO
Green Building Rough 7/6/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 7/6/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/26/2022 Approved SABAS ALONSO
Final 10/26/2022 Corrections Issued SABAS ALONSO
Green Building Final 10/26/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 10/26/2022 Approved SABAS ALONSO
Final 11/3/2022 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved SABAS ALONSO
Final 11/10/2022 Conditional Approval SABAS ALONSO
Final 12/16/2022 OK to Issue CofO SABAS ALONSO