13765 W JUDD ST 91331

Certificate Information: 13765 W JUDD ST 91331

Application / Permit
21010-20000-03917
Plan Check / Job No.
B21VN10128
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY 44'-3" X 27'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Building Plans Picked Up 9/22/2020 APPLICANT
Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 COLIN LOREDO
Corrections Issued 9/8/2021 COLIN LOREDO
Quality Review Completed 9/17/2021 OMID HEDAYAT
Applicant returned to address corrections 6/7/2022 COLIN LOREDO
Plan Check Approved 12/15/2022 MARVEL DELACRUZ
Issued 12/15/2022 APPLICANT
CofO in Progress 11/20/2024 MICHEL ABAJAN
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/20/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/25/2021 CARLOS AGUILERA
Sewer availability Cleared 10/25/2021 CARLOS AGUILERA
ZI Cleared 11/12/2021 MARITZA PRZEKOP
Low Impact Development Cleared 2/8/2022 KHAING AYE
Construction within easement Cleared 2/15/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 2/19/2022 LAURINDA MEADE
Roof/Waste drainage to street Cleared 4/1/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 4/12/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
METHANE-Subgrade 4/12/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/12/2023 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/17/2023 Not Ready for Inspection MICHEL ABAJAN
METHANE-Barrier 4/17/2023 Not Ready for Inspection MICHEL ABAJAN
METHANE-Subgrade 4/17/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 5/2/2023 Not Ready for Inspection MATTHEW NELSON
METHANE-Barrier 5/2/2023 Corrections Issued MATTHEW NELSON
METHANE-Subgrade 5/2/2023 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 8/21/2023 Approved MICHEL ABAJAN
METHANE-Barrier 8/21/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 8/21/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 12/20/2023 Corrections Issued MICHEL ABAJAN
HVAC-Rough 12/20/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/20/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 12/20/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 12/28/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 12/28/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/29/2023 Approved MICHEL ABAJAN
Green Building Rough 12/29/2023 Approved MICHEL ABAJAN
METHANE-Rough 12/29/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 12/29/2023 Approved MICHEL ABAJAN
Insulation 1/3/2024 Corrections Issued JOSE AVILA
Insulation 1/8/2024 Approved KEVIN BERBERYAN
Drywall Nailing 1/16/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Not Ready MICHEL ABAJAN
Sewer 4/8/2024 Approved MICHEL ABAJAN
Underground Mechanical 4/8/2024 Partial Approval MICHEL ABAJAN
Underground Mechanical 4/11/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 5/22/2024 Not Ready for Inspection MICHEL ABAJAN
Final 5/22/2024 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 5/22/2024 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 5/22/2024 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 5/22/2024 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 5/22/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 5/22/2024 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 7/9/2024 Approved MICHEL ABAJAN
HVAC-Final 7/9/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Final 8/8/2024 Approved MICHEL ABAJAN
Final 8/8/2024 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 8/8/2024 Approved MICHEL ABAJAN
HVAC-Final 8/8/2024 Approved MICHEL ABAJAN
PLUMBING-Final 8/8/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 8/8/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 8/8/2024 Approved MICHEL ABAJAN
Final 10/21/2024 Corrections Issued MICHEL ABAJAN
Service/Power Release 10/21/2024 Not Ready for Inspection MICHEL ABAJAN
Final 11/20/2024 OK to Issue CofO MICHEL ABAJAN