5119 S ASCOT AVE 90011

Certificate Information: 5119 S ASCOT AVE 90011

Application / Permit
21010-20000-03909
Plan Check / Job No.
B21VN10108
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLan ADU addition. Existing 2-car Garage 386 s.f. to be converted into ADU, add 149.5 s.f. to ADU. consisting of 2-bedrooms, 1-bath and open kitchen, dining & living area.
Permit Issued
Issued on 8/29/2022
Issuing Office
Current Status
CofO Issued on 7/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 JOSEPH RAFOLS
Corrections Issued 8/14/2021 HERNAN ARREOLA
Applicant returned to address corrections 7/16/2022 JOSEPH RAFOLS
Plan Check Approved 8/2/2022 JOSEPH RAFOLS
Issued 8/29/2022 APPLICANT
CofO in Progress 7/18/2023 BRENDAN MORELLI
Permit Finaled 7/23/2023 DEROLD HAUFF
CofO Issued 7/23/2023 DEROLD HAUFF
Permit Finaled 7/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/22/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/22/2022 JEANETTE VONG
Construction near power lines Cleared 4/1/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/15/2022 JEANETTE VONG
Sewer availability Cleared 7/15/2022 JEANETTE VONG
Tenant Habitability Plan Cleared 8/2/2022 LUIS ALVAREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/4/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/10/2022 Approved RYAN SALAZAR
ELECTRICAL-Rough 12/16/2022 Approved BRENDAN MORELLI
PLUMBING-Rough 12/16/2022 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 12/21/2022 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 1/3/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/3/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/10/2023 Partial Approval BRENDAN MORELLI
Insulation 1/18/2023 Corrections Issued BRENDAN MORELLI
Drywall Nailing 1/27/2023 Corrections Issued BRENDAN MORELLI
Green Building Rough 1/27/2023 Approved BRENDAN MORELLI
Gas Test 5/5/2023 Approved BRENDAN MORELLI
Underground Mechanical 5/5/2023 Partial Approval BRENDAN MORELLI
Sewer 5/16/2023 Corrections Issued BRENDAN MORELLI
Sewer 5/22/2023 Approved BRENDAN MORELLI
Drywall Nailing 6/1/2023 Approved BRENDAN MORELLI
Final 6/1/2023 Corrections Issued BRENDAN MORELLI
Green Building Final 6/1/2023 Conditional Approval BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 6/1/2023 Approved BRENDAN MORELLI
Final 6/26/2023 Corrections Issued BRENDAN MORELLI
Green Building Final 6/26/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Not Ready BRENDAN MORELLI
ELECTRICAL-Final 7/6/2023 Corrections Issued BRENDAN MORELLI
Final 7/6/2023 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Approved BRENDAN MORELLI
Final 7/17/2023 OK to Issue CofO BRENDAN MORELLI