5119 S ASCOT AVE 90011
Certificate Information: 5119 S ASCOT AVE 90011
- Application / Permit
- 21010-20000-03909
- Plan Check / Job No.
- B21VN10108
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLan ADU addition. Existing 2-car Garage 386 s.f. to be converted into ADU, add 149.5 s.f. to ADU. consisting of 2-bedrooms, 1-bath and open kitchen, dining & living area.
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Current Status
- CofO Issued on 7/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2021 | JOSEPH RAFOLS |
| Corrections Issued | 8/14/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/16/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 8/2/2022 | JOSEPH RAFOLS |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 7/18/2023 | BRENDAN MORELLI |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
| CofO Issued | 7/23/2023 | DEROLD HAUFF |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 4/1/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/15/2022 | JEANETTE VONG |
| Tenant Habitability Plan | Cleared | 8/2/2022 | LUIS ALVAREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/4/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 11/10/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/16/2022 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 12/16/2022 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/21/2022 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/3/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/10/2023 | Partial Approval | BRENDAN MORELLI |
| Insulation | 1/18/2023 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 1/27/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Rough | 1/27/2023 | Approved | BRENDAN MORELLI |
| Gas Test | 5/5/2023 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 5/5/2023 | Partial Approval | BRENDAN MORELLI |
| Sewer | 5/16/2023 | Corrections Issued | BRENDAN MORELLI |
| Sewer | 5/22/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 6/1/2023 | Approved | BRENDAN MORELLI |
| Final | 6/1/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 6/1/2023 | Conditional Approval | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 6/1/2023 | Approved | BRENDAN MORELLI |
| Final | 6/26/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 6/26/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Not Ready | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/6/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 7/6/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | BRENDAN MORELLI |
| Final | 7/17/2023 | OK to Issue CofO | BRENDAN MORELLI |