23448 W JUSTICE ST 91304
Certificate Information: 23448 W JUSTICE ST 91304
- Application / Permit
- 21010-20000-03898
- Plan Check / Job No.
- B21VN10086
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT PER STANDARD PLAN 34
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- Issued on 12/6/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2021 | KEVIN MORALES |
| Corrections Issued | 8/17/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 11/8/2021 | KEVIN MORALES |
| Plan Check Approved | 11/29/2021 | KEVIN MORALES |
| Issued | 12/6/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/18/2021 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 9/15/2021 | TIMOTHY POWELL |
| Hydrant and Access approval | Cleared | 10/14/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 10/16/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/4/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/4/2021 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 11/29/2021 | KEVIN MORALES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/19/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/8/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 2/8/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 3/17/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/17/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/17/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Wood Frame | 3/17/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/21/2022 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 3/21/2022 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/24/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/24/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/24/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/24/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/24/2022 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 3/24/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/1/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/5/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/11/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/11/2022 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 4/19/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/26/2022 | Approved | JUSTIN HAWLEY |
| Insulation | 4/27/2022 | Corrections Issued | JUSTIN HAWLEY |
| Shower Pan | 5/2/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 5/11/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 8/3/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 8/3/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 8/3/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/3/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/17/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 8/17/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 8/17/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 8/17/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 8/17/2022 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 8/17/2022 | Not Required | CHRIS CHRISTENSEN |
| Final | 12/15/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 12/15/2022 | Approved | CHRIS CHRISTENSEN |