9639 N BARTEE AVE 91331
Certificate Information: 9639 N BARTEE AVE 91331
- Application / Permit
- 21010-20000-03891
- Plan Check / Job No.
- B21VN10069
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan Check* NEW DETACHED ACCESSORY DWELLING AT REAR OF LOT (476 SQ.FT.). PER ORDINANCE AND LAMC 12.22 A 33 (c) &(d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- CofO Issued on 11/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | ZAW HAN |
| Corrections Issued | 8/5/2021 | ZAW HAN |
| Plan Check Approved | 2/8/2022 | ZAW HAN |
| Issued | 3/10/2022 | APPLICANT |
| CofO in Progress | 11/8/2022 | MICHEL ABAJAN |
| CofO Issued | 11/14/2022 | RONALD MYRICK |
| Permit Finaled | 11/14/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 10/15/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/28/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Adu Guys.Com Inc The; Lic. No.: 1071442-B | 512 N AVALON BLVD WILMINGTON, CA 90744 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/22/2022 | Corrections Issued | MICHEL ABAJAN |
| Underground Mechanical | 3/22/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/11/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/11/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Reinf. Concrete | 4/12/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/10/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/10/2022 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Rough | 5/10/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 5/10/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/10/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 5/10/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/19/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/19/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/19/2022 | Approved | MICHEL ABAJAN |
| Insulation | 5/23/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/2/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/18/2022 | Approved | MICHEL ABAJAN |
| Final | 8/18/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 8/18/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 8/18/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 8/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/18/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 8/18/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 8/18/2022 | Approved | MICHEL ABAJAN |
| Final | 11/8/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 11/8/2022 | Approved | MICHEL ABAJAN |