4303 N VALLEY MEADOW ROAD 91436

Certificate Information: 4303 N VALLEY MEADOW ROAD 91436

Application / Permit
21010-20000-03889
Plan Check / Job No.
B21VN10067
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 53'6" X 17' DETACHED ACCESORY DWELLING UNIT AS PER GCS 65852(E)(1)(B) , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofO Issued on 3/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 RARES BODEA
Corrections Issued 9/2/2021 RARES BODEA
Quality Review Completed 9/2/2021 STEVEN KIM
Building Plans Picked Up 9/10/2021 APPLICANT
Applicant returned to address corrections 11/1/2021 RARES BODEA
Applicant returned to address corrections 11/18/2021 RARES BODEA
Plan Check Approved 11/23/2021 RARES BODEA
Issued 4/13/2022 APPLICANT
CofO in Progress 1/28/2025 JOHN COLEMAN
CofO Issued 3/10/2025 JOHN JANSON
Permit Finaled 3/10/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 9/15/2021 CARLOS AGUILERA
Street Frontage Cleared 9/15/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/17/2021 CARLOS AGUILERA
Sewer availability Cleared 9/17/2021 CARLOS AGUILERA
Distance to fire station Cleared 9/25/2021 ROBERT DUFF
Hydrant and Access approval Cleared 9/28/2021 ROBERT DUFF
Low Impact Development Cleared 10/1/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/7/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/8/2022 Approved ROBERT GOLD
Underground Mechanical 6/13/2022 Approved MORRIS JACKSON
Deputy Reinf. Concrete 6/22/2022 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 6/24/2022 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 6/27/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 7/5/2022 Approved VINCENT HANLEY
Reinforced Concrete Frame 7/6/2022 Approved DAVID SANDOVAL
Deputy Shotcrete 7/8/2022 Conditional Approval MICHAEL SMITH
Deputy Reinf. Concrete 12/9/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 12/29/2022 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 12/30/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 6/15/2023 Approved VINCENT HANLEY
HVAC-Rough 12/8/2023 Approved VINCENT HANLEY
PLUMBING-Rough 12/8/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/20/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/12/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Approved VINCENT HANLEY
Green Building Rough 2/12/2024 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 2/12/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/12/2024 Partial Approval VINCENT HANLEY
Gas Test 3/22/2024 Partial Approval VINCENT HANLEY
Insulation 3/22/2024 Approved VINCENT HANLEY
Shower Pan 3/22/2024 Approved VINCENT HANLEY
Underground Mechanical 3/22/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/1/2024 Approved VINCENT HANLEY
Drywall Nailing 4/1/2024 Approved VINCENT HANLEY
Green Building Rough 4/1/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/1/2024 Approved VINCENT HANLEY
HVAC-Final 11/12/2024 Conditional Approval THOMAS FINNILA
PLUMBING-Final 12/2/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 1/15/2025 Approved MORRIS JACKSON
Final 1/24/2025 Not Ready for Inspection JOHN COLEMAN
Green Building Final 1/24/2025 Corrections Issued JOHN COLEMAN
HVAC-Final 1/24/2025 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Approved JOHN COLEMAN
Service/Power Release 1/24/2025 Not Ready for Inspection JOHN COLEMAN
Smoke Detectors 1/24/2025 Approved JOHN COLEMAN
Final 1/28/2025 OK to Issue CofO JOHN COLEMAN
Green Building Final 1/28/2025 Approved JOHN COLEMAN
Service/Power Release 1/28/2025 Approved JOHN COLEMAN