675 N MUSKINGUM AVE 90272

Certificate Information: 675 N MUSKINGUM AVE 90272

Application / Permit
21010-20000-03887
Plan Check / Job No.
B21VN10062
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/ATT 2-CAR GARAGE AND BASEMENT WITH ATT. TRELLIS ( 68'-7"X38'-0") - 1 OF 3, WITH PREFAB TRUSS ;FIRE SPRINKLER NFPA 13D; "COMPLY WITH DEPARTMENT ORDER effective date 09/13/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 9/7/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 MOHAMMAD ESMAILI
Corrections Issued 9/10/2021 MOHAMMAD ESMAILI
Quality Review Completed 9/10/2021 OMID HEDAYAT
Building Plans Picked Up 9/14/2021 APPLICANT
Applicant returned to address corrections 5/28/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/10/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/15/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/17/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/19/2022 MOHAMMAD ESMAILI
Plan Check Approved 8/25/2022 MOHAMMAD ESMAILI
Issued 9/7/2022 APPLICANT
CofO in Progress 6/27/2024 EVAN COOPER
Permit Finaled 7/2/2024 DANIEL ORRANTE
CofO Issued 7/2/2024 DANIEL ORRANTE
Permit Finaled 7/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/9/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 11/9/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 11/9/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 11/9/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 11/9/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 11/9/2021 DINAH GARIN
Permit Cleared 11/9/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/10/2021 DINAH GARIN
Sewer availability Cleared 11/10/2021 DINAH GARIN
Trees in Parkway Cleared 12/14/2021 ADALBERTO VERA
Low Impact Development Cleared 12/21/2021 CHRIS VONG
Distance to fire station Cleared 1/29/2022 RUEL COLE
Hydrant and Access approval Cleared 1/29/2022 RUEL COLE
Construction near power lines Cleared 3/31/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 5/5/2022 DINAH GARIN
GPI Written Notices Cleared 5/27/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 5/27/2022 MOHAMMAD ESMAILI
Miscellaneous Cleared 5/27/2022 MOHAMMAD ESMAILI
Excavation more than 5-ft deep Cleared 9/7/2022 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Approved ANDREW NAVE
Piling/Pier/Caisson 9/27/2022 Partial Approval BRENDAN LOONEY
Deputy Reinf. Concrete 9/28/2022 Conditional Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/6/2022 Corrections Issued BRENDAN LOONEY
Underground Mechanical 12/6/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/21/2022 Not Ready for Inspection BRENDAN LOONEY
Piling/Pier/Caisson 12/21/2022 Not Ready for Inspection BRENDAN LOONEY
Underground Mechanical 12/21/2022 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 12/22/2022 Conditional Approval BRENDAN LOONEY
Underground Mechanical 12/22/2022 Approved BRENDAN LOONEY
Underground Mechanical 12/23/2022 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 12/29/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 12/29/2022 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 1/6/2023 Not Ready for Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 1/11/2023 Partial Approval BRENDAN LOONEY
Deputy Shotcrete 1/26/2023 Conditional Approval BRENDAN LOONEY
Reinforced Concrete Frame 1/27/2023 Partial Approval BRENDAN LOONEY
Deputy Shotcrete 1/31/2023 Conditional Approval MICHAEL PELHAM
Special/Order Compliance 3/30/2023 Partial Inspection KENNETH NAGLE
Deputy Drilled-In Anchors 4/10/2023 Approved KENNETH NAGLE
Footing/Foundation/Slab 4/10/2023 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 4/11/2023 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Corrections Issued BRENDAN LOONEY
Special/Order Compliance 4/26/2023 Approved BRENDAN LOONEY
Deputy Reinf. Concrete 5/1/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/4/2023 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 5/17/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 5/31/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/12/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/12/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/14/2023 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/14/2023 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/16/2023 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/16/2023 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/16/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/16/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/20/2023 Corrections Issued KENNETH NAGLE
Verify Sprinkler Sign Off 6/20/2023 Not Ready for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/21/2023 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 6/22/2023 Partial Approval RICHARD STEINBACH
Insulation 6/26/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 7/3/2023 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 7/3/2023 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 7/3/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Shower Pan 7/3/2023 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 7/3/2023 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 7/6/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Shower Pan 7/6/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 7/6/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Insulation 7/11/2023 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 7/14/2023 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/14/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 7/18/2023 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 7/18/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sewer 9/11/2023 Partial Approval ARAM AVEDISIAN
Sewer 10/2/2023 Partial Approval EVAN COOPER
Sewer 11/15/2023 No Access for Inspection KENNETH NAGLE
Gas Test 11/16/2023 Partial Approval EVAN COOPER
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Not Ready EVAN COOPER
Sewer 11/16/2023 Approved EVAN COOPER
Underground Mechanical 11/16/2023 Approved EVAN COOPER
HVAC-Final 3/28/2024 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 3/28/2024 Not Ready for Inspection EVAN COOPER
HVAC-Final 4/3/2024 Corrections Issued EVAN COOPER
PLUMBING-Final 4/3/2024 Corrections Issued EVAN COOPER
ELECTRICAL-Final 4/10/2024 Approved EVAN COOPER
Final 4/10/2024 Corrections Issued EVAN COOPER
Gas Test 4/10/2024 Approved EVAN COOPER
HVAC-Final 4/10/2024 Approved EVAN COOPER
PLUMBING-Final 4/10/2024 Approved EVAN COOPER
Final 4/24/2024 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 4/24/2024 Approved EVAN COOPER
Green Building Final 4/24/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Approved EVAN COOPER
Service/Power Release 4/24/2024 Not Ready for Inspection EVAN COOPER
Smoke Detectors 4/24/2024 Approved EVAN COOPER
Final 5/22/2024 Not Ready for Inspection EVAN COOPER
Service/Power Release 5/22/2024 Not Ready for Inspection EVAN COOPER
Final 6/12/2024 Not Ready for Inspection EVAN COOPER
Service/Power Release 6/12/2024 Not Ready for Inspection EVAN COOPER
Final 6/17/2024 Not Ready for Inspection EVAN COOPER
Service/Power Release 6/17/2024 Not Ready for Inspection EVAN COOPER
Final 6/25/2024 Conditional Approval EVAN COOPER
Service/Power Release 6/25/2024 Approved EVAN COOPER
Final 6/27/2024 OK to Issue CofO EVAN COOPER