Floor/Roof Diaphrgm/Shear Wall
|
9/20/2022
|
Approved
|
ANDREW NAVE
|
|
Piling/Pier/Caisson
|
9/27/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Deputy Reinf. Concrete
|
9/28/2022
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
12/6/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Underground Mechanical
|
12/6/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
12/21/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Piling/Pier/Caisson
|
12/21/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Underground Mechanical
|
12/21/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
12/22/2022
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Underground Mechanical
|
12/22/2022
|
Approved
|
BRENDAN LOONEY
|
|
Underground Mechanical
|
12/23/2022
|
Partial Approval
|
KENNETH NAGLE
|
|
Excavation/Setback/Form/Re-Bar
|
12/29/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
PLUMBING-Rough
|
12/29/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
1/6/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
1/11/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
Deputy Shotcrete
|
1/26/2023
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Reinforced Concrete Frame
|
1/27/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
Deputy Shotcrete
|
1/31/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Special/Order Compliance
|
3/30/2023
|
Partial Inspection
|
KENNETH NAGLE
|
|
Deputy Drilled-In Anchors
|
4/10/2023
|
Approved
|
KENNETH NAGLE
|
|
Footing/Foundation/Slab
|
4/10/2023
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
4/11/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/20/2023
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Special/Order Compliance
|
4/26/2023
|
Approved
|
BRENDAN LOONEY
|
|
Deputy Reinf. Concrete
|
5/1/2023
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/4/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/17/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Special/Order Compliance
|
5/17/2023
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/18/2023
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Wood Construction
|
5/31/2023
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/31/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/7/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Rough
|
6/12/2023
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
6/12/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Rough
|
6/14/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/14/2023
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
HVAC-Rough
|
6/14/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Rough
|
6/16/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
HVAC-Rough
|
6/16/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
6/16/2023
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
6/16/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
BUILDING-Rough-Frame
|
6/20/2023
|
Corrections Issued
|
KENNETH NAGLE
|
|
Verify Sprinkler Sign Off
|
6/20/2023
|
Not Ready for Inspection
|
KENNETH NAGLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/21/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
6/21/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Interior/Exterior Lathing
|
6/22/2023
|
Partial Approval
|
RICHARD STEINBACH
|
|
Insulation
|
6/26/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
BUILDING-Rough-Frame
|
7/3/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Green Building Rough
|
7/3/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
7/3/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Shower Pan
|
7/3/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Verify Sprinkler Sign Off
|
7/3/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
7/6/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Shower Pan
|
7/6/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Special/Order Compliance
|
7/6/2023
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
7/11/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
7/14/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Interior/Exterior Lathing
|
7/14/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Drywall Nailing
|
7/18/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Interior/Exterior Lathing
|
7/18/2023
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Sewer
|
9/11/2023
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Sewer
|
10/2/2023
|
Partial Approval
|
EVAN COOPER
|
|
Sewer
|
11/15/2023
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Gas Test
|
11/16/2023
|
Partial Approval
|
EVAN COOPER
|
|
SGSOV-Seismic Gas S/O Valve
|
11/16/2023
|
SGSOV Not Ready
|
EVAN COOPER
|
|
Sewer
|
11/16/2023
|
Approved
|
EVAN COOPER
|
|
Underground Mechanical
|
11/16/2023
|
Approved
|
EVAN COOPER
|
|
HVAC-Final
|
3/28/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
PLUMBING-Final
|
3/28/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
HVAC-Final
|
4/3/2024
|
Corrections Issued
|
EVAN COOPER
|
|
PLUMBING-Final
|
4/3/2024
|
Corrections Issued
|
EVAN COOPER
|
|
ELECTRICAL-Final
|
4/10/2024
|
Approved
|
EVAN COOPER
|
|
Final
|
4/10/2024
|
Corrections Issued
|
EVAN COOPER
|
|
Gas Test
|
4/10/2024
|
Approved
|
EVAN COOPER
|
|
HVAC-Final
|
4/10/2024
|
Approved
|
EVAN COOPER
|
|
PLUMBING-Final
|
4/10/2024
|
Approved
|
EVAN COOPER
|
|
Final
|
4/24/2024
|
Corrections Issued
|
EVAN COOPER
|
|
Footing/Foundation/Slab
|
4/24/2024
|
Approved
|
EVAN COOPER
|
|
Green Building Final
|
4/24/2024
|
Approved
|
EVAN COOPER
|
|
SGSOV-Seismic Gas S/O Valve
|
4/24/2024
|
SGSOV Approved
|
EVAN COOPER
|
|
Service/Power Release
|
4/24/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Smoke Detectors
|
4/24/2024
|
Approved
|
EVAN COOPER
|
|
Final
|
5/22/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Service/Power Release
|
5/22/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Final
|
6/12/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Service/Power Release
|
6/12/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Final
|
6/17/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Service/Power Release
|
6/17/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Final
|
6/25/2024
|
Conditional Approval
|
EVAN COOPER
|
|
Service/Power Release
|
6/25/2024
|
Approved
|
EVAN COOPER
|
|
Final
|
6/27/2024
|
OK to Issue CofO
|
EVAN COOPER
|