16103 W HARVEST ST 91344

Certificate Information: 16103 W HARVEST ST 91344

Application / Permit
21010-20000-03876
Plan Check / Job No.
B21VN10029
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 29'-3" X 40'-1" IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/21/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Assigned to Plan Check Engineer 9/21/2021 JEROME MAGAT PALMA
Corrections Issued 9/21/2021 JEROME MAGAT PALMA
Building Plans Picked Up 10/25/2021 APPLICANT
Plan Check Approved 9/27/2022 SERGIO MUNIZ
Issued 12/21/2022 APPLICANT
CofO in Progress 12/3/2024 JAVIER RAMOS JR
Permit Finaled 12/4/2024 RUBEN SALAS
CofO Issued 12/4/2024 RUBEN SALAS
Permit Finaled 12/4/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/9/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 2/9/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 2/9/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 7/26/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/2/2022 JOSE DUARTE-DIAZ
GPI Written Notices Cleared 9/13/2022 TIMOTHY POWELL
Grading Pre-Inspection Cleared 9/13/2022 TIMOTHY POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/24/2023 No Access for Inspection JAVIER RAMOS JR
PLUMBING-Rough 4/28/2023 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 5/25/2023 Corrections Issued JAVIER RAMOS JR
Wood Frame 10/12/2023 Partial Inspection JAVIER RAMOS JR
Deputy Wood Construction 10/23/2023 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 1/23/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/6/2024 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 3/13/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/9/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 4/9/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 4/9/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 4/9/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/9/2024 Partial Approval JAVIER RAMOS JR
Underground Mechanical 4/9/2024 Partial Approval JAVIER RAMOS JR
Insulation 4/16/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/29/2024 Partial Approval JAVIER RAMOS JR
Drywall Nailing 4/29/2024 Partial Approval JAVIER RAMOS JR
Green Building Rough 4/29/2024 Approved JAVIER RAMOS JR
Insulation 4/29/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 10/7/2024 Approved KEVIN BERBERYAN
Drywall Nailing 10/7/2024 Approved KEVIN BERBERYAN
Final 10/7/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 10/7/2024 Approved KEVIN BERBERYAN
Green Building Final 10/7/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 10/7/2024 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 10/7/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 10/7/2024 Approved KEVIN BERBERYAN
Final 10/10/2024 No Access for Inspection JAVIER RAMOS JR
Service/Power Release 10/10/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 10/21/2024 Corrections Issued ROBERT GOLD
Service/Power Release 10/21/2024 Not Ready for Inspection ROBERT GOLD
Final 11/4/2024 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 11/4/2024 Not Ready for Inspection JENNIFER RABUCHIN
Final 12/3/2024 OK to Issue CofO JAVIER RAMOS JR