1637 N GENESEE AVE 90046

Certificate Information: 1637 N GENESEE AVE 90046

Application / Permit
21010-20000-03872
Plan Check / Job No.
B21VN10009
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHEAD (15'-3"x25'-0"),633 SQFT ADU W/NFPA 13D SPRINKLERS THROUGHOUT PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 7/18/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 PETER MOSESIAN
Corrections Issued 8/26/2021 PETER MOSESIAN
Quality Review Completed 8/27/2021 OMID HEDAYAT
Building Plans Picked Up 9/1/2021 APPLICANT
Plan Check Approved 5/18/2022 PETER MOSESIAN
Issued 7/18/2022 APPLICANT
CofO in Progress 1/15/2025 BRIAN SULLIVAN
Permit Finaled 1/18/2025 DEROLD HAUFF
CofO Issued 1/18/2025 DEROLD HAUFF
Permit Finaled 1/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/30/2021 CHRISTOPHER ROCHA
Street Frontage Cleared 11/30/2021 CHRISTOPHER ROCHA
HPOZ Cleared 12/23/2021 AMANDA KAINER
ZI Cleared 12/23/2021 AMANDA KAINER
ZA Case Cleared 12/29/2021 PABLO ESTRADA
Low Impact Development Cleared 3/2/2022 JULIAN SUNG
Hydrant and Access approval Cleared 3/19/2022 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 4/5/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/7/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 6/21/2022 CHRISTOPHER ROCHA

Contact Information

Architect Bray,, Roger Winston; Lic. No.: C25330 17949 HATTON STREET      RESEDA, CA 91335
Contractor Elc Builders Inc; Lic. No.: 900479-B 23810 MOBILE STREET      WEST HILLS, CA 91307
Engineer Greco,, Adam Matthew; Lic. No.: S4077 1470 WESTERLY TERRACE      LOS ANGELES, CA 90026
Landscape Architect Alaniz,, Arthur Louis; Lic. No.: LA5554 26 CLEAR VISTA      ROLLING HILLS ESTATES, CA 90274

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2022 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 12/2/2022 Conditional Approval RAUL BARAJAS
Underground Mechanical 12/8/2022 Approved RAUL BARAJAS
Footing/Foundation/Slab 12/15/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 2/14/2023 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Corrections Issued STUART CHAPMAN
Wood Frame 5/2/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/24/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/13/2023 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 6/13/2023 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 6/13/2023 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Partial Approval STUART CHAPMAN
HVAC-Rough 7/18/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/21/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 7/21/2023 Approved STUART CHAPMAN
Green Building Rough 7/21/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 7/21/2023 Approved STUART CHAPMAN
Shower Pan 9/12/2023 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 9/21/2023 Approved RAUL BARAJAS
Insulation 10/5/2023 Approved STUART CHAPMAN
Drywall Nailing 10/18/2023 Approved STUART CHAPMAN
Green Building Rough 10/18/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/30/2023 Approved RONNIE MINDANAO
ELECTRICAL-Final 3/14/2024 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 6/3/2024 Approved BRIAN SULLIVAN
HVAC-Final 6/6/2024 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Final 6/27/2024 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 8/15/2024 Approved BRIAN SULLIVAN
Final 8/15/2024 Corrections Issued BRIAN SULLIVAN
Green Building Final 8/15/2024 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/15/2024 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 8/15/2024 Not Ready for Inspection BRIAN SULLIVAN
Smoke Detectors 8/15/2024 Approved BRIAN SULLIVAN
Final 9/11/2024 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 9/11/2024 Not Ready for Inspection BRIAN SULLIVAN
Final 10/1/2024 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 10/1/2024 Approved BRIAN SULLIVAN
Final 1/15/2025 OK to Issue CofO BRIAN SULLIVAN