18012 W BULLOCK ST 91316
Certificate Information: 18012 W BULLOCK ST 91316
- Application / Permit
- 21010-20000-03863
- Plan Check / Job No.
- B21VN09933
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY 24'-0" X 22'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 9/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | COLIN LOREDO |
| Corrections Issued | 9/9/2021 | COLIN LOREDO |
| Quality Review Completed | 9/17/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| Plan Check Approved | 5/11/2022 | JON BLAINE |
| Issued | 5/11/2022 | APPLICANT |
| CofO in Progress | 9/8/2022 | SEAN HAUPT |
| CofO Issued | 9/15/2022 | MICHAEL SMITH |
| Permit Finaled | 9/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/8/2021 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 11/18/2021 | RIDWAN HARDY |
| ZI | Cleared | 11/24/2021 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 1/16/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 1/27/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 2/2/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: C53256 | 11607 AMESTOY AVE GRANADA HILLS, CA 91344 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/24/2022 | Partial Approval | SEAN HAUPT |
| Underground Mechanical | 5/24/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 5/27/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 5/27/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Approved | SEAN HAUPT |
| Gas Test | 6/9/2022 | Approved | SEAN HAUPT |
| Sewer | 6/9/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 6/9/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 6/30/2022 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Conditional Approval | SEAN HAUPT |
| HVAC-Rough | 6/30/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 6/30/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/7/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 7/7/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 7/7/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 7/7/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 7/7/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 7/7/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 7/7/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 7/14/2022 | Approved | SEAN HAUPT |
| Shower Pan | 7/14/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 7/15/2022 | Approved | SEAN HAUPT |
| Shower Pan | 7/15/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 7/26/2022 | Approved | SEAN HAUPT |
| Final | 9/6/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 9/6/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 9/6/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 9/6/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 9/7/2022 | Approved | SEAN HAUPT |
| Final | 9/7/2022 | Partial Approval | SEAN HAUPT |
| HVAC-Final | 9/7/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 9/7/2022 | Approved | SEAN HAUPT |
| Service/Power Release | 9/7/2022 | Approved | SEAN HAUPT |
| Service/Power Release | 9/15/2022 | Approved | SEAN HAUPT |