15146 W PLUMMER ST 91343

Certificate Information: 15146 W PLUMMER ST 91343

Application / Permit
21010-20000-03858
Plan Check / Job No.
B21VN09924
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & WFPP [The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy]
Permit Issued
Issued on 2/2/2022
Issuing Office
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 NILOOFAR MEHRAIN
Corrections Issued 9/7/2021 NILOOFAR MEHRAIN
Quality Review Completed 9/14/2021 STEVEN KIM
Building Plans Picked Up 9/16/2021 APPLICANT
Plan Check Approved 1/26/2022 NILOOFAR MEHRAIN
Issued 2/2/2022 APPLICANT
CofO in Progress 1/14/2023 GREGG CUMMINGS
CofO Issued 1/21/2023 MICHAEL SMITH
Permit Finaled 1/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/24/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/29/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/29/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 1/11/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/15/2022 Corrections Issued WILLIAM WREN
Excavation/Setback/Form/Re-Bar 4/21/2022 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 4/21/2022 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 4/25/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 4/25/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 4/25/2022 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 5/27/2022 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 5/27/2022 Corrections Issued GREGG CUMMINGS
Wood Frame 5/27/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 6/3/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 6/3/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 6/3/2022 Approved GREGG CUMMINGS
Underground Mechanical 6/3/2022 Partial Approval GREGG CUMMINGS
Underground Mechanical 6/13/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/17/2022 Partial Approval GREGG CUMMINGS
Green Building Rough 6/17/2022 Approved GREGG CUMMINGS
HVAC-Rough 6/17/2022 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 6/17/2022 Approved GREGG CUMMINGS
Insulation 6/27/2022 Approved WILLIAM WREN
Sewer 7/6/2022 Corrections Issued GREGG CUMMINGS
Sewer 7/11/2022 Approved GREGG CUMMINGS
Drywall Nailing 7/15/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/15/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 12/29/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 12/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 12/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Gas Test 12/29/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 12/29/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 12/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 12/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 12/29/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 12/29/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 1/13/2023 Approved GREGG CUMMINGS
Final 1/13/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 1/13/2023 Approved GREGG CUMMINGS
PLUMBING-Final 1/13/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/13/2023 SGSOV Approved GREGG CUMMINGS
Service/Power Release 1/13/2023 Approved GREGG CUMMINGS