4356 N ALLOTT AVE 91423

Certificate Information: 4356 N ALLOTT AVE 91423

Application / Permit
21010-20000-03831
Plan Check / Job No.
B21VN09851
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 69'-2" X 33' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/9/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 SELLA BENYAMIN
Corrections Issued 9/7/2021 SELLA BENYAMIN
Quality Review Completed 9/20/2021 STEVEN KIM
Building Plans Picked Up 9/21/2021 APPLICANT
Applicant returned to address corrections 3/21/2022 SELLA BENYAMIN
Plan Check Approved 7/29/2022 SELLA BENYAMIN
Issued 8/9/2022 APPLICANT
CofO in Progress 8/23/2023 MISAEL ESPARZA
Permit Finaled 9/27/2023 RUBEN SALAS
CofO Issued 9/27/2023 RUBEN SALAS
Permit Finaled 9/27/2023 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 11/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/29/2021 CARLOS AGUILERA
Sewer availability Cleared 11/29/2021 CARLOS AGUILERA
Low Impact Development Cleared 1/10/2022 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 1/11/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/13/2022 KURT CORRAL
ZI Cleared 2/4/2022 MIGUEL GAMBOA
Trees in Parkway Cleared 2/16/2022 ADALBERTO VERA

Contact Information

Contractor Basen Construction Inc; Lic. No.: 1074082-B 201 N REESE PL UNIT 101      BURBANK, CA 91506
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/31/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 9/8/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/15/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 11/16/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval MISAEL ESPARZA
Wood Frame 11/21/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 2/7/2023 Corrections Issued MISAEL ESPARZA
HVAC-Rough 2/16/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 2/16/2023 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 2/24/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 2/27/2023 Corrections Issued MISAEL ESPARZA
HVAC-Rough 2/27/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/27/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/28/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/28/2023 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 2/28/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 3/10/2023 Approved MISAEL ESPARZA
HVAC-Rough 3/10/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 3/10/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/24/2023 Approved MISAEL ESPARZA
Green Building Rough 3/24/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/24/2023 Partial Approval MISAEL ESPARZA
Insulation 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 4/7/2023 Approved MISAEL ESPARZA
Shower Pan 4/25/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/1/2023 Approved MISAEL ESPARZA
Sewer 5/8/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/7/2023 Corrections Issued MISAEL ESPARZA
Final 7/7/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 7/7/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 7/7/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 7/7/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 7/7/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 7/7/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 8/10/2023 Conditional Approval MISAEL ESPARZA
Final 8/10/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 8/10/2023 Approved MISAEL ESPARZA
HVAC-Final 8/10/2023 Approved MISAEL ESPARZA
PLUMBING-Final 8/10/2023 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 8/10/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 8/10/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 8/15/2023 Approved MISAEL ESPARZA
HVAC-Final 8/15/2023 Approved MISAEL ESPARZA
PLUMBING-Final 8/15/2023 Approved MISAEL ESPARZA
Service/Power Release 8/22/2023 Approved MISAEL ESPARZA
Final 8/23/2023 OK to Issue CofO MISAEL ESPARZA
Smoke Detectors 8/23/2023 Approved MISAEL ESPARZA