17030 W RANCHO ST 91316

Certificate Information: 17030 W RANCHO ST 91316

Application / Permit
21010-20000-03711
Plan Check / Job No.
B21VN09791
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 10'-11" x 21'-0" DET. REC ROOM W/ 1/2 BATHROOM AND OUTDOOR SHOWER; AUTOMATIC SPRINKLER SYSTEM IS REQ'D
Permit Issued
Issued on 2/24/2022
Issuing Office
Current Status
CofO Issued on 11/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 SEAN SHAHMIRI
Corrections Issued 8/15/2021 SEAN SHAHMIRI
Quality Review Completed 8/18/2021 OMID HEDAYAT
Building Plans Picked Up 8/24/2021 APPLICANT
Applicant returned to address corrections 10/7/2021 SEAN SHAHMIRI
Plan Check Approved 2/16/2022 SEAN SHAHMIRI
Applicant returned to address corrections 2/17/2022 SEAN SHAHMIRI
Issued 2/24/2022 APPLICANT
CofO in Progress 9/8/2023 VINCENT HANLEY
CofO Issued 11/6/2023 JOHN JANSON
Permit Finaled 11/6/2023 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 11/17/2021 CARLOS AGUILERA
Watercourse Cleared 11/17/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/20/2021 CARLOS AGUILERA
ZA Case Cleared 1/7/2022 LAUREN PADICK
Hydrant and Access approval Cleared 1/27/2022 MATTHEW CRAIG
Low Impact Development Cleared 2/3/2022 NICK RAYGOZA
Roof/Waste drainage to street Cleared 2/7/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 2/16/2022 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/8/2022 Approved SEAN HAUPT
PLUMBING-Rough 4/8/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 7/18/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 12/1/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/14/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/14/2022 Approved VINCENT HANLEY
Green Building Rough 12/14/2022 Approved VINCENT HANLEY
HVAC-Rough 12/14/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 12/14/2022 Approved VINCENT HANLEY
Insulation 12/22/2022 Approved VINCENT HANLEY
Shower Pan 12/22/2022 Approved VINCENT HANLEY
Drywall Nailing 1/5/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 6/21/2023 Approved JOHN KIDWELL
PLUMBING-Final 6/21/2023 Approved JOHN KIDWELL
Final 9/7/2023 OK to Issue CofO VINCENT HANLEY
Green Building Final 9/7/2023 Approved VINCENT HANLEY
HVAC-Final 9/7/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 9/7/2023 Approved VINCENT HANLEY
Smoke Detectors 9/7/2023 Approved VINCENT HANLEY