14833 W ERWIN ST 1-6 91411
Certificate Information: 14833 W ERWIN ST 1-6 91411
- Application / Permit
- 21010-20000-03705
- Plan Check / Job No.
- B21VN09758
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 81'2" X 32' THREE STORY 5 UNIT APARTMENT WITH ATTACHED (1) ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (E) (TYPE V A ) WITH 1 CAR GARAGE ATTACHED AT 1ST FLOOR , NFPA-13R FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2021 | APPLICANT |
| Green Plans Picked Up | 8/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | RARES BODEA |
| Disabled Access Plans Picked Up | 8/18/2021 | APPLICANT |
| Corrections Issued | 8/23/2021 | RARES BODEA |
| Quality Review Completed | 8/25/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/25/2021 | APPLICANT |
| Applicant returned to address corrections | 9/27/2021 | RARES BODEA |
| Applicant returned to address corrections | 11/30/2021 | RARES BODEA |
| Applicant returned to address corrections | 12/27/2021 | RARES BODEA |
| Plan Check Approved | 2/2/2022 | RARES BODEA |
| Issued | 3/3/2022 | APPLICANT |
| CofO in Progress | 1/5/2023 | CAMERON CHABAN |
| Permit Finaled | 1/23/2023 | RICKEY JACKSON |
| CofO Issued | 1/23/2023 | RICKEY JACKSON |
| Permit Finaled | 1/23/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2021 | CARLOS AGUILERA |
| Highway dedication | Cleared | 8/23/2021 | CARLOS AGUILERA |
| Permit | Cleared | 8/23/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 9/2/2021 | JOHN KIM |
| Frnt yard landscape/Water mgmt | Cleared | 9/13/2021 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 9/17/2021 | KURT CORRAL |
| Green Code | Cleared | 9/21/2021 | MICHAEL AYERS |
| Fire Marshall Fire Life Safety | Cleared | 9/22/2021 | WILLIAM JOHNS |
| DAS Clearance | Cleared | 11/10/2021 | OLLIE CARTER |
| Low Impact Development | Cleared | 12/16/2021 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/20/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Dream Home Design; Lic. No.: 1058115-B | 14759 FRIAR STREET VAN NUYS, CA 91411 |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/9/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Wood Construction | 4/4/2022 | Conditional Approval | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Partial Approval | CAMERON CHABAN |
| Green Building Rough | 4/4/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 4/4/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Wood Frame | 4/4/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Wood Construction | 4/19/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 5/11/2022 | Partial Approval | CAMERON CHABAN |
| Green Building Rough | 5/11/2022 | Partial Inspection | CAMERON CHABAN |
| Insulation | 5/11/2022 | Partial Approval | CAMERON CHABAN |
| Interior/Exterior Lathing | 6/7/2022 | Corrections Issued | JOHN KITCKO |
| Wall Anchors | 6/7/2022 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Drilled-In Anchors | 6/13/2022 | Conditional Approval | JOHN KITCKO |
| Green Building Rough | 6/14/2022 | Approved | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 6/14/2022 | Conditional Approval | CAMERON CHABAN |
| Wall Anchors | 6/14/2022 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 6/14/2022 | Partial Inspection | CAMERON CHABAN |
| Interior/Exterior Lathing | 6/15/2022 | Conditional Approval | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 6/16/2022 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 6/16/2022 | Conditional Approval | CAMERON CHABAN |
| Insulation | 6/21/2022 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 6/28/2022 | Approved | CAMERON CHABAN |
| Special/Order Compliance | 9/23/2022 | Partial Inspection | JOHN KITCKO |
| Final | 11/22/2022 | Partial Inspection | CAMERON CHABAN |
| Footing/Foundation/Slab | 11/22/2022 | Approved | CAMERON CHABAN |
| Green Building Final | 11/22/2022 | Partial Inspection | CAMERON CHABAN |
| Reinforced Concrete Frame | 11/22/2022 | Approved | CAMERON CHABAN |
| Reinforced Masonry Frame | 11/22/2022 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Not Ready | CAMERON CHABAN |
| Smoke Detectors | 11/22/2022 | Approved | CAMERON CHABAN |
| Structural Steel Frame | 11/22/2022 | Approved | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 11/22/2022 | Approved | CAMERON CHABAN |
| Wood Frame | 11/22/2022 | Approved | CAMERON CHABAN |
| Final | 1/5/2023 | OK to Issue CofO | CAMERON CHABAN |
| Green Building Final | 1/5/2023 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Approved | CAMERON CHABAN |