11129 W LULL ST 91352
Certificate Information: 11129 W LULL ST 91352
- Application / Permit
- 21010-20000-03701
- Plan Check / Job No.
- B21VN09753
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER STATE LAW (1-STORY) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 1/26/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | CARLOS MONTES |
| Corrections Issued | 8/20/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 1/19/2022 | CARLOS MONTES |
| Plan Check Approved | 1/21/2022 | CARLOS MONTES |
| Issued | 1/26/2022 | APPLICANT |
| CofO in Progress | 2/27/2023 | MATTHEW NELSON |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/27/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/24/2021 | DAGOVERTO GUERRERO |
| Clean Up Green Up | Cleared | 10/5/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 1/11/2022 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/19/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/19/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 6/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 6/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 6/23/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/29/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 6/29/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/21/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 7/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 7/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/29/2022 | No Access for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 9/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 9/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 9/9/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 9/15/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 9/29/2022 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 10/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 1/19/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 1/19/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/19/2023 | Approved | MATTHEW NELSON |
| HVAC-Final | 1/19/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 1/19/2023 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/19/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 1/19/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 1/19/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 2/1/2023 | Approved | MATTHEW NELSON |
| Final | 2/1/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 2/1/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 2/1/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 2/1/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 2/27/2023 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 2/27/2023 | Approved | MATTHEW NELSON |
| Service/Power Release | 2/27/2023 | Approved | MATTHEW NELSON |