12544 1/2 W VANOWEN ST 91605

Certificate Information: 12544 1/2 W VANOWEN ST 91605

Application / Permit
21010-20000-03675
Plan Check / Job No.
B21VN09651
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU. New Accessory dwelling unit by Installing a RADCO Approved Factory Built Housing Unit over a raised floor foundation per LADBS ADU Standard Plan ADU29. Factory Built Housing per RAD-31-1030. per GCS 65852.2(e)(1)(D)
Permit Issued
Issued on 10/21/2021
Issuing Office
Current Status
CofO Issued on 3/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2021 APPLICANT
Assigned to Plan Check Engineer 7/27/2021 MONICA RAMIREZ
Corrections Issued 7/28/2021 MONICA RAMIREZ
Applicant returned to address corrections 9/27/2021 MONICA RAMIREZ
Plan Check Approved 10/15/2021 MONICA RAMIREZ
Issued 10/21/2021 APPLICANT
CofO in Progress 3/3/2023 KIRK SANDERS
CofO Issued 3/6/2023 MICHAEL SMITH
Permit Finaled 3/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/31/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/4/2021 GABRIEL ROBLES
Sewer availability Cleared 8/4/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/31/2021 GABRIEL ROBLES

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B       ,
Engineer Farish,, William Crawford; Lic. No.: C30123 19432 CASTLEWOOD CR      HUNTINGTON BEACH, CA 92648
Engineer Sveiven,, Shane; Lic. No.: C89133 1909 S ALMA STREET      SAN PEDRO, CA 90731

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/17/2022 Not Ready for Inspection JOSEPH NICOSIA
Sewer 5/17/2022 Not Ready for Inspection JOSEPH NICOSIA
Underground Mechanical 5/17/2022 Partial Approval JOSEPH NICOSIA
Footing/Foundation/Slab 5/18/2022 Approved CHRISTOPHE COCHRAN
Underground Mechanical 5/24/2022 Partial Inspection ARPAD BODOLAI
Underground Mechanical 5/26/2022 Partial Approval ARPAD BODOLAI
BUILDING-Rough-Frame 6/7/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 6/7/2022 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 6/7/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 6/29/2022 Approved HERBERT GIRON
Underground Mechanical 11/21/2022 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Not Ready KIRK SANDERS
Final 3/2/2023 OK to Issue CofO KIRK SANDERS
Green Building Final 3/2/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 3/2/2023 Approved KIRK SANDERS
Smoke Detectors 3/2/2023 Approved KIRK SANDERS