17834 W ROSCOE BLVD 91325
Certificate Information: 17834 W ROSCOE BLVD 91325
- Application / Permit
- 21010-20000-03664
- Plan Check / Job No.
- B21VN09587
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2 STORY ADU (20'-0"x31'-4"), 1200 SQFT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 11/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | PETER MOSESIAN |
| Corrections Issued | 8/28/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/13/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/16/2021 | APPLICANT |
| Plan Check Approved | 2/3/2022 | PETER MOSESIAN |
| Issued | 3/15/2022 | APPLICANT |
| CofO in Progress | 10/13/2022 | SEAN HAUPT |
| Permit Finaled | 11/1/2022 | JOHN JANSON |
| CofO Issued | 11/1/2022 | JOHN JANSON |
| Permit Finaled | 11/1/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/20/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/20/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/20/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 1/24/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Romero General Builders Inc; Lic. No.: 1074956-B | 14153 1/2 BERGSTROM PL SYLMAR, CA 91342 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/5/2022 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/5/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/5/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/15/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 4/15/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 4/15/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/15/2022 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 4/15/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/3/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/3/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/3/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/3/2022 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 6/3/2022 | Approved | VINCENT HANLEY |
| Wood Frame | 6/3/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/16/2022 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 6/29/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 7/5/2022 | Approved | JEFFREY BULL |
| Shower Pan | 7/5/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 9/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| Final | 9/26/2022 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 9/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Final | 9/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 9/26/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 9/26/2022 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 9/26/2022 | Approved | JEFFREY BULL |
| Final | 10/12/2022 | Partial Approval | SEAN HAUPT |
| Green Building Final | 10/12/2022 | Approved | SEAN HAUPT |
| Service/Power Release | 10/12/2022 | Approved | SEAN HAUPT |