1810 N OLD ORCHARD ROAD 90049

Certificate Information: 1810 N OLD ORCHARD ROAD 90049

Application / Permit
21010-20000-03653
Plan Check / Job No.
B21VN09556
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (76'-6"x 67'-6") 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 2/16/2022
Issuing Office
Current Status
CofO Issued on 4/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 TROY DEGUZMAN
Corrections Issued 8/7/2021 TROY DEGUZMAN
Quality Review Completed 8/9/2021 OMID HEDAYAT
Building Plans Picked Up 8/17/2021 APPLICANT
Applicant returned to address corrections 1/27/2022 TROY DEGUZMAN
Plan Check Approved 2/11/2022 TROY DEGUZMAN
Issued 2/16/2022 APPLICANT
CofO in Progress 4/17/2024 KEVIN SARGSYAN
Permit Finaled 4/22/2024 DANIEL ORRANTE
CofO Issued 4/22/2024 DANIEL ORRANTE
Permit Finaled 4/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/27/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 9/27/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 9/27/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 9/27/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 9/27/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 9/27/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/28/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/28/2021 HISASHI KOBAYAKAWA
Watercourse Cleared 9/28/2021 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 10/1/2021 KURT CORRAL
Low Impact Development Cleared 11/16/2021 LONDY ALVARADO
GPI Written Notices Cleared 1/27/2022 VASIL MIHALEV
Grading Pre-Inspection Cleared 1/27/2022 VASIL MIHALEV
Green Code Cleared 1/27/2022 TROY DEGUZMAN
Permit Cleared 1/27/2022 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 1/27/2022 ADALBERTO VERA
Roof/Waste drainage to street Cleared 2/7/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/21/2022 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/12/2022 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 5/16/2022 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 5/18/2022 Approved JUAN VALENZUELA
Deputy Steel/Welding 6/15/2022 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 10/3/2022 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 10/6/2022 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 10/6/2022 Corrections Issued JUAN VALENZUELA
Gas Test 10/12/2022 Approved CARLOS MATAMOROS
HVAC-Rough 10/12/2022 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 10/12/2022 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Corrections Issued JUAN VALENZUELA
FLOOD-Proofing Certificate 12/19/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Corrections Issued JUAN VALENZUELA
Green Building Rough 12/19/2022 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 12/19/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Partial Approval KEVIN SARGSYAN
Green Building Rough 2/13/2023 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 3/28/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 4/3/2023 Corrections Issued KEVIN SARGSYAN
Green Building Rough 4/3/2023 Approved KEVIN SARGSYAN
HVAC-Rough 4/3/2023 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 4/11/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 4/11/2023 Approved KEVIN SARGSYAN
HVAC-Rough 4/11/2023 Approved KEVIN SARGSYAN
Insulation 4/17/2023 Approved KEVIN SARGSYAN
Drywall Nailing 4/25/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 4/25/2023 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 5/1/2023 Approved KEVIN SARGSYAN
Shower Pan 5/1/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 3/13/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 3/13/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 3/14/2024 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 3/19/2024 Approved KEVIN SARGSYAN
HVAC-Final 3/19/2024 Approved KEVIN SARGSYAN
Final 4/1/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/1/2024 Approved KEVIN SARGSYAN
Green Building Final 4/1/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 4/1/2024 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 4/1/2024 Approved KEVIN SARGSYAN
Final 4/16/2024 OK to Issue CofO KEVIN SARGSYAN
Service/Power Release 4/16/2024 Approved KEVIN SARGSYAN