7352 N BECKFORD AVE 91335

Certificate Information: 7352 N BECKFORD AVE 91335

Application / Permit
21010-20000-03652
Plan Check / Job No.
B21VN09554
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 11'X16', 150 SQ. FT. RECREATION ROOM PER ENGINEERING.
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 3/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 COLIN LOREDO
Corrections Issued 8/5/2021 COLIN LOREDO
Applicant returned to address corrections 9/8/2021 COLIN LOREDO
Building Plans Picked Up 9/10/2021 APPLICANT
Plan Check Approved 9/23/2021 COLIN LOREDO
Issued 9/28/2021 APPLICANT
CofO in Progress 2/14/2022 VINCENT HANLEY
Permit Finaled 3/4/2022 JOHN JANSON
CofO Issued 3/4/2022 JOHN JANSON
Permit Finaled 3/4/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/13/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/13/2021 CARLOS AGUILERA
Sewer availability Cleared 9/13/2021 CARLOS AGUILERA

Contact Information

Contractor Cohen David; Lic. No.: 466645-B 5145 YARMOUTH AVENUE #7      ENCINO, CA 91316
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2021 Approved VINCENT HANLEY
PLUMBING-Rough 10/12/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 11/1/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 11/1/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/1/2021 Approved VINCENT HANLEY
PLUMBING-Rough 11/1/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/9/2021 Partial Approval VINCENT HANLEY
Green Building Rough 11/9/2021 Approved VINCENT HANLEY
Insulation 11/9/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/9/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/3/2021 Approved VINCENT HANLEY
Drywall Nailing 12/3/2021 Approved VINCENT HANLEY
Final 12/3/2021 Corrections Issued VINCENT HANLEY
Green Building Final 12/3/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/3/2021 SGSOV Gas Company VINCENT HANLEY
Service/Power Release 12/3/2021 Approved VINCENT HANLEY
Smoke Detectors 12/3/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 12/3/2021 Not Ready for Inspection VINCENT HANLEY
Final 2/14/2022 OK to Issue CofO VINCENT HANLEY