802 N GALLOWAY ST 90272

Certificate Information: 802 N GALLOWAY ST 90272

Application / Permit
21010-20000-03646
Plan Check / Job No.
B21VN09494
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 73' X 34' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/28/2022
Issuing Office
Current Status
CofO Issued on 11/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 SELLA BENYAMIN
Corrections Issued 8/23/2021 SELLA BENYAMIN
Quality Review Completed 8/27/2021 STEVEN KIM
Building Plans Picked Up 9/1/2021 APPLICANT
Plan Check Approved 2/26/2022 SELLA BENYAMIN
Issued 2/28/2022 APPLICANT
CofO in Progress 9/22/2023 OGANES TARAKHCHYAN
Permit Finaled 11/3/2023 DANIEL ORRANTE
CofO Issued 11/3/2023 DANIEL ORRANTE
Permit Finaled 11/3/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/10/2021 CECILIO NAVARRO
Permit Cleared 9/22/2021 ANTHONY MAINEZ
Sewer availability Cleared 9/23/2021 ANTHONY MAINEZ
Address approval Cleared 10/7/2021 ANTHONY MAINEZ
Low Impact Development Cleared 1/3/2022 CHRIS PARK
Roof/Waste drainage to street Cleared 1/4/2022 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 1/27/2022 KURT CORRAL
Trees in Parkway Cleared 2/11/2022 ADALBERTO VERA
GPI Written Notices Cleared 2/26/2022 SELLA BENYAMIN
Grading Pre-Inspection Cleared 2/26/2022 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/29/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 4/4/2022 Not Ready for Inspection JOHN KIDWELL
Deputy Reinf. Concrete 4/6/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Partial Approval JOHN KIDWELL
Green Building Rough 6/9/2022 Not Ready for Inspection JUAN VALENZUELA
Pre-Inspection 6/9/2022 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 6/9/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 6/14/2022 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 6/15/2022 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 6/15/2022 Partial Inspection MICHAEL PELHAM
PLUMBING-Rough 6/15/2022 Approved MICHAEL PELHAM
ELECTRICAL-Rough 6/17/2022 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Approval JOHN KIDWELL
HVAC-Rough 6/27/2022 Approved JOHN KIDWELL
HVAC-Rough 6/28/2022 Not Ready for Inspection JOHN KIDWELL
Grading Pre-Inspection 7/14/2022 Partial Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/29/2022 Corrections Issued OGANES TARAKHCHYAN
Deputy Wood Construction 8/1/2022 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 8/5/2022 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 8/10/2022 Corrections Issued STEPHANIE SWANSON
Green Building Rough 8/10/2022 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 8/10/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 8/18/2022 Approved BRENDAN LOONEY
Pre-Inspection 8/18/2022 Corrections Issued BRENDAN LOONEY
Shower Pan 8/18/2022 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 8/23/2022 Approved KEVIN SARGSYAN
Insulation 8/23/2022 Approved KEVIN SARGSYAN
Drywall Nailing 8/30/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/30/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 5/1/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 5/2/2023 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 5/10/2023 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Final 5/23/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 6/6/2023 Partial Approval OGANES TARAKHCHYAN
Service/Power Release 8/31/2023 Approved KENNETH NAGLE
Final 9/13/2023 No Access for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/13/2023 Approved OGANES TARAKHCHYAN
Green Building Final 9/13/2023 No Access for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 9/13/2023 Approved OGANES TARAKHCHYAN
Final 9/21/2023 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 9/21/2023 Approved OGANES TARAKHCHYAN