3122 N FARNSWORTH AVE 90032
Certificate Information: 3122 N FARNSWORTH AVE 90032
- Application / Permit
- 21010-20000-03632
- Plan Check / Job No.
- B21VN09447
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26' X 32'-6" (800 SF) DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g). ALL WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2021 | OMAR GARNICA |
| Corrections Issued | 7/28/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 9/7/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 10/15/2021 | OMAR GARNICA |
| Plan Check Approved | 10/28/2021 | OMAR GARNICA |
| Issued | 10/28/2021 | APPLICANT |
| Building Plans Picked Up | 10/28/2021 | APPLICANT |
| CofO in Progress | 3/14/2024 | LILIANA PORTILLO |
| CofO Issued | 3/19/2024 | DEROLD HAUFF |
| Permit Finaled | 3/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 8/11/2021 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/12/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/25/2021 | RUEL COLE |
| GPI Written Notices | Cleared | 10/15/2021 | OMAR GARNICA |
| Roof/Waste drainage to street | Cleared | 10/22/2021 | JEANIE LAM |
Contact Information
| Architect | Yasharel,, Harry H; Lic. No.: C14933 | 4524 WHITE OAK PLACE ENCINO, CA 91316 |
| Contractor | Addition Building & Design Inc; Lic. No.: 925471-B | 4335 VAN NUYS BLVD STE 354 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/24/2021 | Partial Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 12/2/2021 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 12/2/2021 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 12/4/2021 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/4/2021 | Off-Hour Fees Due | |
| Pre-Inspection | 12/4/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/7/2021 | Not Ready for Inspection | COREY HUPP |
| Deputy Wood Construction | 12/16/2021 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/20/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 1/6/2022 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 1/6/2022 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 1/6/2022 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 1/19/2022 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/19/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 1/19/2022 | Approved | LILIANA PORTILLO |
| Insulation | 1/19/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 1/19/2022 | Partial Inspection | LILIANA PORTILLO |
| Sewer | 1/24/2022 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/24/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/7/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 2/7/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/7/2022 | Partial Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/24/2022 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/1/2022 | Approved | AMY COLIN |
| Final | 4/1/2022 | Partial Inspection | AMY COLIN |
| Footing/Foundation/Slab | 4/1/2022 | Partial Inspection | AMY COLIN |
| Green Building Final | 4/1/2022 | Corrections Issued | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2022 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 4/1/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 4/1/2022 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 4/1/2022 | Approved | AMY COLIN |
| Final | 5/16/2022 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/16/2022 | Approved | OSVALDO PARAMO |
| Green Building Final | 5/16/2022 | Approved | OSVALDO PARAMO |
| Service/Power Release | 5/16/2022 | Approved | OSVALDO PARAMO |
| Final | 3/13/2024 | OK to Issue CofO | LILIANA PORTILLO |