11024 W PENROSE ST 91352
Certificate Information: 11024 W PENROSE ST 91352
- Application / Permit
- 21010-20000-03628
- Plan Check / Job No.
- B21VN09442
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN - NEW DETACHED 1200 SF ADU
- Permit Issued
- Issued on 8/8/2022
- Issuing Office
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2021 | JOE VO |
| Corrections Issued | 7/29/2021 | CARLOS MONTES |
| Plan Check Approved | 7/30/2022 | JOE VO |
| Issued | 8/8/2022 | APPLICANT |
| CofO in Progress | 3/12/2025 | DAVID ANDERSON |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
| CofO Issued | 4/1/2025 | RUBEN SALAS |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 4/26/2022 | WALTER RAMIREZ |
| Clean Up Green Up | Cleared | 6/6/2022 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 7/21/2022 | ROGELIO CORTES |
| Hydrant and Access approval | Cleared | 7/27/2022 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 7/28/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/1/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 6/16/2023 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 6/23/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Corrections Issued | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 7/17/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 7/27/2023 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 8/14/2023 | Approved | DAVID ANDERSON |
| Sewer | 8/14/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 8/14/2023 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/14/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/18/2023 | Corrections Issued | DAVID ANDERSON |
| Deputy Wood Construction | 9/28/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/29/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 9/29/2023 | Approved | DAVID ANDERSON |
| Insulation | 10/17/2023 | Corrections Issued | DAVID ANDERSON |
| Insulation | 11/7/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/7/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 11/27/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 12/22/2023 | Approved | DAVID ANDERSON |
| Final | 6/4/2024 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 6/4/2024 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | DAVID MATSON |
| Service/Power Release | 6/4/2024 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 6/4/2024 | Corrections Issued | DAVID MATSON |
| ELECTRICAL-Final | 6/27/2024 | Approved | DAVID ANDERSON |
| Gas Test | 11/5/2024 | Approved | DAVID ANDERSON |
| Final | 1/27/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 1/27/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 1/27/2025 | Approved | DAVID ANDERSON |
| Final | 3/11/2025 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 3/11/2025 | Approved | DAVID ANDERSON |