8926 W OLIN ST 90034
Certificate Information: 8926 W OLIN ST 90034
- Application / Permit
- 21010-20000-03599
- Plan Check / Job No.
- B21VN09351
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 11'-1" x 18'-0" ONE-STORY DET. ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g); AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 3/29/2022
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | SEAN SHAHMIRI |
| Corrections Issued | 8/6/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 8/9/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| Plan Check Approved | 3/29/2022 | SEAN SHAHMIRI |
| Issued | 3/29/2022 | APPLICANT |
| CofO in Progress | 10/31/2023 | MICHAEL PELHAM |
| CofO in Progress | 10/31/2023 | MICHAEL PELHAM |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
| CofO Issued | 11/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/3/2021 | JORGE MEJIA LEMUS |
| Construction near power lines | Cleared | 11/8/2021 | RIDWAN HARDY |
| Address approval | Cleared | 11/15/2021 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 11/15/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | CINDY QI |
| Sewer availability | Cleared | 11/16/2021 | CINDY QI |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/12/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/12/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/24/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 5/25/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 9/26/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 9/26/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 10/11/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 10/11/2022 | Approved | EVAN COOPER |
| Insulation | 11/2/2022 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 11/2/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 11/14/2022 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 11/14/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 7/24/2023 | Corrections Issued | ARAM AVEDISIAN |
| Gas Test | 7/24/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 7/24/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/11/2023 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 10/11/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 10/11/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 10/11/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 10/11/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| MERV13>=Final | 10/11/2023 | Approved | MEL KHACHATOURIAN |
| MERV13>=Rough | 10/11/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 10/11/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Service/Power Release | 10/11/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Smoke Detectors | 10/11/2023 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 10/11/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/17/2023 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 10/17/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 10/17/2023 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Final | 10/17/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Service/Power Release | 10/17/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 10/17/2023 | Approved | MEL KHACHATOURIAN |
| Final | 10/27/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Service/Power Release | 10/27/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 10/31/2023 | OK to Issue CofO | MICHAEL PELHAM |
| Service/Power Release | 10/31/2023 | Approved | MICHAEL PELHAM |