17623 W WEDDINGTON ST 91316

Certificate Information: 17623 W WEDDINGTON ST 91316

Application / Permit
21010-20000-03594
Plan Check / Job No.
B21VN09340
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 86'-4" X 64'-6" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
CofO Issued on 3/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 SELLA BENYAMIN
Corrections Issued 8/23/2021 SELLA BENYAMIN
Quality Review Completed 8/27/2021 STEVEN KIM
Building Plans Picked Up 8/31/2021 APPLICANT
Plan Check Approved 12/3/2021 SELLA BENYAMIN
Issued 12/6/2021 APPLICANT
CofO in Progress 12/28/2022 SEAN HAUPT
Permit Finaled 3/24/2023 JOHN JANSON
CofO Issued 3/24/2023 JOHN JANSON
Permit Finaled 3/24/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/12/2021 CARLOS AGUILERA
Permit Cleared 10/12/2021 CARLOS AGUILERA
Sewer availability Cleared 10/12/2021 CARLOS AGUILERA
Low Impact Development Cleared 10/19/2021 TA ANH
Hydrant and Access approval Cleared 10/21/2021 KURT CORRAL
Roof/Waste drainage to street Cleared 10/26/2021 CARLOS AGUILERA
Trees in Parkway Cleared 11/17/2021 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/8/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 2/17/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 2/17/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/7/2022 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Approved SEAN HAUPT
PLUMBING-Rough 4/6/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 4/14/2022 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 4/21/2022 Approved SEAN HAUPT
HVAC-Rough 4/26/2022 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 5/20/2022 Approved SEAN HAUPT
Green Building Rough 5/20/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 5/20/2022 Approved SEAN HAUPT
HVAC-Rough 5/26/2022 Approved SEAN HAUPT
Drywall Nailing 6/3/2022 Approved SEAN HAUPT
Final 12/9/2022 Corrections Issued SEAN HAUPT
Green Building Final 12/9/2022 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 12/9/2022 Approved SEAN HAUPT
Smoke Detectors 12/9/2022 Approved SEAN HAUPT
Final 12/27/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 12/27/2022 Approved SEAN HAUPT