6448 N SUNNYSLOPE AVE 91401
Certificate Information: 6448 N SUNNYSLOPE AVE 91401
- Application / Permit
- 21010-20000-03572
- Plan Check / Job No.
- B21VN09282
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY 89'-8" X 43'-6" SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE AND ATTACHED PATIO. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | COLIN LOREDO |
| Corrections Issued | 8/24/2021 | COLIN LOREDO |
| Quality Review Completed | 9/1/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| Applicant returned to address corrections | 5/26/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 6/17/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 7/1/2022 | COLIN LOREDO |
| Plan Check Approved | 7/21/2022 | COLIN LOREDO |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 5/24/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 6/11/2024 | RUBEN SALAS |
| Permit Finaled | 6/11/2024 | RUBEN SALAS |
| CofO Issued | 6/11/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Permit | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/26/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 11/22/2021 | PABLO ESTRADA |
| Hydrant and Access approval | Cleared | 12/7/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 1/10/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 1/10/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/29/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/13/2022 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/5/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 4/5/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 4/5/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/4/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 5/4/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 5/4/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 5/4/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 5/4/2023 | Partial Approval | KIRK SANDERS |
| Verify Sprinkler Sign Off | 5/4/2023 | Approved | KIRK SANDERS |
| Insulation | 5/18/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 6/7/2023 | Approved | KIRK SANDERS |
| Shower Pan | 6/30/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/7/2023 | Approved | KIRK SANDERS |
| Sewer | 11/6/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 11/6/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Final | 1/5/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 1/25/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 1/25/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 2/28/2024 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 2/28/2024 | Conditional Approval | JOSE AVILA |
| PLUMBING-Final | 2/28/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 3/5/2024 | Approved | JOSE AVILA |
| Final | 5/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/10/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 5/16/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Service/Power Release | 5/16/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 5/16/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 5/23/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |