7807 S BROADWAY 1-20 90003
Certificate Information: 7807 S BROADWAY 1-20 90003
- Application / Permit
- 21010-20000-03569
- Plan Check / Job No.
- B21VN09260
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 103'7" X 38' THREE STORY 20 UNIT APARTMENT FULLY SPRINKLERED NFPA-13R (TYPE V-A CONSTRUCTION ) ( TOC, TIER 1 ( INCREASE TO TIER 2 - 100% AFFORDABLE HOUSING TO INCLUDE 2 UNITS EXTREMELY LOW INCOME UNITS, 2 UNITS VERY LOW INCOME, 16 UNITS LOW INCOME) [PER ADM-2021-5136-TOC], ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- Valley
- Current Status
- Issued on 10/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 7/28/2021 | APPLICANT |
| Green Plans Picked Up | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | RARES BODEA |
| Corrections Issued | 8/31/2021 | RARES BODEA |
| Quality Review Completed | 9/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/2/2021 | APPLICANT |
| Plan Check Approved | 7/21/2023 | RARES BODEA |
| Issued | 10/18/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 9/8/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | WALLIE JONG |
| Highway dedication | Cleared | 9/9/2021 | WALLIE JONG |
| DCP conditions approval | Cleared | 4/28/2022 | RICHARD TRUONG |
| Density Bonus 12.22.A.31 | Cleared | 4/28/2022 | RICHARD TRUONG |
| Density Bonus 12.22.A.31 | Cleared | 4/28/2022 | RICHARD TRUONG |
| Density Bonus 12.22.A.31 | Cleared | 4/28/2022 | RICHARD TRUONG |
| Miscellaneous | Cleared | 5/4/2022 | STEVEN WECHSLER |
| Building over 3-story or 36-ft | Cleared | 5/5/2022 | CALOSHA APPROVED |
| Frnt yard landscape/Water mgmt | Cleared | 5/20/2022 | STEVEN WECHSLER |
| Opn space landscape/Water mgmt | Cleared | 5/20/2022 | STEVEN WECHSLER |
| Sewer availability | Cleared | 5/20/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 8/9/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 8/17/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | WALLIE JONG |
| Fire Marshall Fire Life Safety | Cleared | 9/27/2022 | DOMINIQUE MEDINA |
| DAS Clearance | Cleared | 10/24/2022 | OLLIE CARTER |
| Green Code | Cleared | 11/3/2022 | MICHAEL AYERS |
| Redevelopment Project Area | Cleared | 1/18/2023 | DAVID URITA |
| Community Plan Implem. Overlay | Cleared | 1/23/2023 | ADALBERTO VERA |
| Community Plan Implem. Overlay | Cleared | 2/1/2023 | MOHAMMAD HASAN |
| Community Plan Implem. Overlay | Cleared | 2/6/2023 | WALTER RAMIREZ |
| Community Plan Implem. Overlay | Cleared | 6/13/2023 | HELEN JADALI |
Contact Information
| Contractor | Ndrbuilds Inc; Lic. No.: 508255-B | 2929 CALMGARDEN ROAD ACTON, CA 93510 |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/22/2024 | Partial Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 5/3/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/22/2024 | Conditional Approval | ADAM BURGESS |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 5/28/2024 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 5/28/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 6/7/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 6/20/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 9/4/2024 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 9/4/2024 | Partial Approval | LARRY ARNICK |
| Special/Order Compliance | 10/9/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 10/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 10/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 12/9/2024 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 12/31/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 12/31/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 1/17/2025 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 2/10/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 2/26/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 2/26/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 3/4/2025 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 4/29/2025 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 11/5/2025 | Approved | JOEY BUCHANAN |
| Wood Frame | 11/5/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 11/7/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 11/13/2025 | Partial Approval | JOEY BUCHANAN |
| Insulation | 11/24/2025 | Partial Approval | JOEY BUCHANAN |
| Insulation | 11/25/2025 | No Access for Inspection | RAFAEL ESPINOZA |
| Insulation | 12/2/2025 | No Access for Inspection | RAFAEL CORTES |
| Pre-Inspection | 12/17/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/16/2026 | Corrections Issued | JOEY BUCHANAN |
| Pre-Inspection | 5/13/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 6/18/2026 | Partial Approval | RAFAEL ESPINOZA |