1343 N OCCIDENTAL BLVD 90026
Certificate Information: 1343 N OCCIDENTAL BLVD 90026
- Application / Permit
- 21010-20000-03539
- Plan Check / Job No.
- B21VN09194
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-11" X 30'-11" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | SELLA BENYAMIN |
| Corrections Issued | 8/2/2021 | SELLA BENYAMIN |
| Quality Review Completed | 8/4/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/5/2021 | APPLICANT |
| Plan Check Approved | 2/15/2022 | SELLA BENYAMIN |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 4/24/2024 | THOMAS LOGRASSO |
| CofO Issued | 5/22/2024 | DEROLD HAUFF |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 10/29/2021 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 1/20/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 1/28/2022 | GILBERT URREA |
| GPI Written Notices | Cleared | 2/15/2022 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 2/15/2022 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boranian,, Paul Darian; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2022 | Partial Inspection | THOMAS LOGRASSO |
| Underground Mechanical | 8/15/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/29/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/31/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 9/21/2023 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 9/27/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/6/2023 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 12/6/2023 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 12/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 12/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Corrections Issued | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 12/20/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/26/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Shower Pan | 1/8/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 1/16/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 1/25/2024 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 1/25/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/6/2024 | No Access for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 2/8/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 3/11/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 3/11/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 3/27/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 3/27/2024 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 4/1/2024 | Partial Approval | THOMAS LOGRASSO |
| Final | 4/10/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/10/2024 | Approved | THOMAS LOGRASSO |
| Green Building Final | 4/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 4/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 4/10/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/12/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/16/2024 | Approved | THOMAS LOGRASSO |
| Final | 4/23/2024 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 4/23/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 4/23/2024 | Approved | THOMAS LOGRASSO |