23151 W CASS AVE 91364
Certificate Information: 23151 W CASS AVE 91364
- Application / Permit
- 21010-20000-03508
- Plan Check / Job No.
- B21VN09076
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Detached ADU with LADBS Pre-Approved Standard Plan (Plan ADU3, Abodu Studio, 336 sq. ft.) Construction of HCD approved and inspected Factory Built Housing ADU. ADU to be fully completed in Factory and installed on Concrete t-footing foundation, connected to site utilities.
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 2/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | JOE VO |
| Corrections Issued | 7/15/2021 | JOE VO |
| Applicant returned to address corrections | 8/3/2021 | JOE VO |
| Plan Check Approved | 10/29/2021 | JOE VO |
| Issued | 1/18/2022 | APPLICANT |
| CofO in Progress | 12/30/2022 | PETER FOLLING |
| Permit Finaled | 2/2/2023 | JOHN JANSON |
| CofO Issued | 2/2/2023 | JOHN JANSON |
| Permit Finaled | 2/2/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/11/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/11/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/11/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/11/2021 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Street Frontage | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Street width determination | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Certificate of Compliance | Cleared | 8/23/2021 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 10/13/2021 | JOE VO |
| Hydrant and Access approval | Cleared | 10/22/2021 | RUEL COLE |
| Miscellaneous | Cleared | 10/22/2021 | RUEL COLE |
Contact Information
| Contractor | Abodu Inc; Lic. No.: 1073522-B | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/4/2022 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 4/11/2022 | Approved | PETER FOLLING |
| Sewer | 4/11/2022 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 10/6/2022 | Partial Inspection | JOHN KIDWELL |
| Pre-Inspection | 11/22/2022 | No Access for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 12/19/2022 | Approved | PETER FOLLING |
| Final | 12/19/2022 | Corrections Issued | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Not Required | PETER FOLLING |
| Service/Power Release | 12/19/2022 | Not Ready for Inspection | PETER FOLLING |
| Smoke Detectors | 12/19/2022 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 12/19/2022 | Approved | PETER FOLLING |
| Final | 12/29/2022 | OK to Issue CofO | PETER FOLLING |
| Service/Power Release | 12/29/2022 | Approved | PETER FOLLING |