8951 N CHIMINEAS AVE 91325
Certificate Information: 8951 N CHIMINEAS AVE 91325
- Application / Permit
- 21010-20000-03505
- Plan Check / Job No.
- B21VN09075
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan new detached ADU with 2 car garage
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- CofO Issued on 9/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 8/21/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/27/2021 | MINYE PAK |
| Plan Check Approved | 12/5/2021 | ARSALAN SHABESTARI |
| Issued | 12/22/2021 | APPLICANT |
| CofO in Progress | 9/1/2022 | JEFFREY PARD |
| Permit Finaled | 9/1/2022 | JOHN JANSON |
| CofO Issued | 9/1/2022 | JOHN JANSON |
| Permit Finaled | 9/1/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 10/7/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/7/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/1/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 11/15/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Simcity Construction Inc; Lic. No.: 1027407-B | 3350 W OLYMOIC BLVD #202 LOS ANGELES, CA 90019 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/28/2022 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 2/28/2022 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 5/5/2022 | Corrections Issued | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Approved | JEFFREY PARD |
| HVAC-Rough | 5/5/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 5/5/2022 | Approved | JEFFREY PARD |
| Wood Frame | 5/5/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 5/10/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 5/10/2022 | Approved | JEFFREY PARD |
| Wood Frame | 5/10/2022 | Approved | JEFFREY PARD |
| Insulation | 5/12/2022 | Not Ready for Inspection | JEFFREY PARD |
| Insulation | 5/16/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 5/24/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/24/2022 | Approved | KRISTEN CAUSEY |
| Sewer | 7/19/2022 | Approved | JEFFREY PARD |
| Underground Mechanical | 7/19/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/17/2022 | Approved | JEFFREY PARD |
| Final | 8/17/2022 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 8/17/2022 | Approved | JEFFREY PARD |
| Gas Test | 8/17/2022 | Approved | JEFFREY PARD |
| Green Building Final | 8/17/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 8/17/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 8/17/2022 | Approved | JEFFREY PARD |
| Smoke Detectors | 8/17/2022 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 8/17/2022 | Approved | JEFFREY PARD |
| Final | 8/30/2022 | OK to Issue CofO | JEFFREY PARD |