20300 W WINDSOR LANE 91326
Certificate Information: 20300 W WINDSOR LANE 91326
- Application / Permit
- 21010-20000-03497
- Plan Check / Job No.
- B21VN09021
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 11'-2" X 17'12" DETACHED OPEN TRELLIS PATIO COVER. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 4/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2021 | LUIS RINCON |
| Corrections Issued | 7/14/2021 | LUIS RINCON |
| Applicant returned to address corrections | 11/15/2021 | LUISANGEL VALENZUELA |
| Issued | 12/2/2021 | APPLICANT |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| CofO in Progress | 4/3/2025 | DAVID SCANTLIN |
| Permit Finaled | 4/7/2025 | JOHN JANSON |
| CofO Issued | 4/7/2025 | JOHN JANSON |
| Permit Finaled | 4/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/14/2021 | LUIS RINCON |
| "T" removal | Cleared | 8/4/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 8/4/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 8/4/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 8/4/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 8/4/2021 | DANG NGUYEN |
| ZA Case | Cleared | 8/4/2021 | DANG NGUYEN |
| ZA Case | Cleared | 8/4/2021 | DANG NGUYEN |
Contact Information
| Contractor | Clark Scott Construction Inc; Lic. No.: 594041-B | 22431 TOUCHSTONE COURT SANTA CLARITA, CA 91390 |
| Engineer | Vinci,, James Richard; Lic. No.: S4411 | 175 E WILBUR ROAD STE 103 THOUSAND OAKS, CA 91360 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/10/2021 | Approved | DAVID SCANTLIN |
| Final | 3/21/2025 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/21/2025 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/21/2025 | Approved | DAVID SCANTLIN |
| Wood Frame | 3/21/2025 | Approved | DAVID SCANTLIN |
| Final | 4/3/2025 | OK to Issue CofO | DAVID SCANTLIN |