10563 N ANDASOL AVE 91344
Certificate Information: 10563 N ANDASOL AVE 91344
- Application / Permit
- 21010-20000-03490
- Plan Check / Job No.
- B21VN08996
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan • NEW DETACHED ADU PER 12.22a33(c) and (b)
- Permit Issued
- Issued on 10/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2021 | HERNAN ARREOLA |
| Corrections Issued | 7/16/2021 | HERNAN ARREOLA |
| Plan Check Approved | 9/25/2021 | HERNAN ARREOLA |
| Issued | 10/21/2021 | APPLICANT |
| CofO in Progress | 5/1/2023 | DAVID SCANTLIN |
| No Progress | 5/16/2023 | JOHN JANSON |
| CofO in Progress | 6/15/2023 | DAVID SCANTLIN |
| Permit Finaled | 6/15/2023 | JOHN JANSON |
| CofO Issued | 6/15/2023 | JOHN JANSON |
| Permit Finaled | 6/15/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/31/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/11/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/17/2021 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 9/21/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 2036 CREEK RD KITTY HAWK, NC 27949 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/25/2022 | Partial Approval | JEFFREY PARD |
| Sewer | 7/25/2022 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 8/10/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/24/2022 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 8/24/2022 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 8/24/2022 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 8/24/2022 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/20/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 9/20/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 9/20/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 9/20/2022 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 9/20/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/30/2022 | Approved | JEFFREY BULL |
| Insulation | 10/11/2022 | Corrections Issued | KRISTEN CAUSEY |
| Drywall Nailing | 10/21/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/21/2022 | Partial Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/3/2022 | Approved | KRISTEN CAUSEY |
| Final | 2/7/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 2/7/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 2/7/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 2/7/2023 | Approved | DAVID SCANTLIN |
| Final | 2/8/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 2/8/2023 | Approved | DAVID SCANTLIN |
| Service/Power Release | 2/8/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Service/Power Release | 3/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 4/28/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Service/Power Release | 4/28/2023 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 5/17/2023 | Corrections Issued | DAVID SCANTLIN |