20600 W OVERLOOK CT 91326

Certificate Information: 20600 W OVERLOOK CT 91326

Application / Permit
21010-20000-03459
Plan Check / Job No.
B21VN08948
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH GARAGE _ PER STANDARD PLAN #655 _PLAN 5BR_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 2/1/2022
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 DAWN MC NULTY
Corrections Issued 8/23/2021 DAWN MC NULTY
Quality Review Completed 8/25/2021 STEVEN KIM
Building Plans Picked Up 8/26/2021 APPLICANT
Applicant returned to address corrections 1/12/2022 DAWN MC NULTY
Plan Check Approved 1/30/2022 DAWN MC NULTY
Issued 2/1/2022 APPLICANT
CofO in Progress 7/15/2023 HENRY KIM
Permit Finaled 7/18/2023 MICHAEL SMITH
CofO Issued 7/18/2023 MICHAEL SMITH
Permit Finaled 7/18/2023 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 11/17/2021 DANG NGUYEN
CPC Cleared 11/17/2021 DANG NGUYEN
CPC Cleared 11/17/2021 DANG NGUYEN
CPC Cleared 11/17/2021 DANG NGUYEN
Tract Map conditions Cleared 11/17/2021 DANG NGUYEN
ZA Case Cleared 11/17/2021 DANG NGUYEN
ZA Case Cleared 11/17/2021 DANG NGUYEN
ZI Cleared 11/17/2021 DANG NGUYEN
Address approval Cleared 12/1/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/1/2021 LEE GUILBEAUX
Permit Cleared 12/1/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/1/2021 LEE GUILBEAUX
Sewer availability Cleared 12/1/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/1/2021 LEE GUILBEAUX
Low Impact Development Cleared 12/16/2021 AMMAR ELTAWIL
Hydrant and Access approval Cleared 1/5/2022 ROBERT DUFF

Contact Information

Architect Swift,, Daniel R; Lic. No.: C32860 4601 WESTOWN PARKWAY SUITE 208      WEST DES MOINES, IA 50266
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Hattar,, Basil Ibrahim; Lic. No.: GE2734 41837 SONOMA ROAD      PALMDALE, CA 93551
Engineer Wong,, Ramon Roman; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/4/2022 No Access for Inspection SEAN WIRCH
Deputy Other (see comments) 5/4/2022 No Access for Inspection SEAN WIRCH
PLUMBING-Rough 8/17/2022 Partial Approval HENRY KIM
Footing/Foundation/Slab 9/14/2022 Corrections Issued HENRY KIM
METHANE-Barrier 9/14/2022 Not Ready for Inspection HENRY KIM
METHANE-Subgrade 9/14/2022 Not Ready for Inspection HENRY KIM
Footing/Foundation/Slab 9/15/2022 Corrections Issued HENRY KIM
METHANE-Barrier 9/15/2022 Approved HENRY KIM
METHANE-Rough 9/15/2022 Approved HENRY KIM
METHANE-Subgrade 9/15/2022 Approved HENRY KIM
Deputy Reinf. Concrete 9/16/2022 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Partial Approval HENRY KIM
Deputy Drilled-In Anchors 10/12/2022 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Corrections Issued HENRY KIM
Deputy Wood Construction 1/24/2023 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval HENRY KIM
Footing/Foundation/Slab 2/2/2023 Approved HENRY KIM
BUILDING-Rough-Frame 2/7/2023 Corrections Issued HENRY KIM
ELECTRICAL-Rough 2/7/2023 Approved HENRY KIM
Green Building Rough 2/7/2023 Approved HENRY KIM
HVAC-Rough 2/7/2023 Approved HENRY KIM
Interior/Exterior Lathing 2/7/2023 Partial Approval HENRY KIM
PLUMBING-Rough 2/7/2023 Approved HENRY KIM
Verify Sprinkler Sign Off 2/7/2023 Approved HENRY KIM
BUILDING-Rough-Frame 2/9/2023 Approved HENRY KIM
Insulation 2/17/2023 Not Ready for Inspection HENRY KIM
Insulation 2/22/2023 Approved JEFFREY PARD
Drywall Nailing 3/1/2023 Approved HENRY KIM
Interior/Exterior Lathing 3/7/2023 Approved HENRY KIM
Sewer 3/8/2023 Approved HENRY KIM
Underground Mechanical 3/8/2023 Approved HENRY KIM
Gas Test 3/31/2023 Approved HENRY KIM
Service/Power Release 4/20/2023 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 4/21/2023 Approved HENRY KIM
Service/Power Release 4/27/2023 Not Ready for Inspection HENRY KIM
Service/Power Release 5/2/2023 Corrections Issued HENRY KIM
Service/Power Release 5/8/2023 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved HENRY KIM
ELECTRICAL-Final 7/7/2023 Corrections Issued HENRY KIM
Final 7/7/2023 Corrections Issued HENRY KIM
Green Building Final 7/7/2023 Approved HENRY KIM
HVAC-Final 7/7/2023 Corrections Issued HENRY KIM
PLUMBING-Final 7/7/2023 Approved HENRY KIM
Smoke Detectors 7/7/2023 Approved HENRY KIM
ELECTRICAL-Final 7/12/2023 Not Ready for Inspection HENRY KIM
Final 7/12/2023 Not Ready for Inspection HENRY KIM
HVAC-Final 7/12/2023 Not Ready for Inspection HENRY KIM
PLUMBING-Final 7/12/2023 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 7/13/2023 Approved HENRY KIM
Final 7/13/2023 Corrections Issued HENRY KIM
HVAC-Final 7/13/2023 Approved HENRY KIM
Final 7/14/2023 OK to Issue CofO HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Approved HENRY KIM