22524-22526 W MACFARLANE DR 91364

Certificate Information: 22524-22526 W MACFARLANE DR 91364

Application / Permit
21010-20000-03444
Plan Check / Job No.
B21VN08924
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan ADU conversion. Convert existing attached garage into new Accessory dwelling unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/27/2022
Issuing Office
Current Status
CofO Issued on 8/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/12/2021 MONICA RAMIREZ
Corrections Issued 7/13/2021 MONICA RAMIREZ
Applicant returned to address corrections 11/19/2021 MONICA RAMIREZ
Plan Check Approved 12/23/2021 JOE VO
Issued 1/27/2022 APPLICANT
CofO in Progress 8/9/2022 PETER FOLLING
Permit Finaled 8/11/2022 JOHN JANSON
CofO Issued 8/11/2022 JOHN JANSON
Permit Finaled 8/11/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/14/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/14/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 7/14/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Doobek Builders; Lic. No.: 980653-B 5308 DERRY AVE   I-101, 102    AGOURA HILLS, CA 91301
Engineer Barakat,, Fouad Chafic; Lic. No.: NA67449       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2022 Approved PETER FOLLING
PLUMBING-Rough 2/10/2022 Partial Approval PETER FOLLING
Sewer 2/10/2022 Approved PETER FOLLING
ELECTRICAL-Rough 3/7/2022 Approved PETER FOLLING
PLUMBING-Rough 3/7/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 4/7/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 4/7/2022 Corrections Issued STEPHANIE SWANSON
Shower Pan 4/7/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 4/12/2022 Partial Approval MORRIS JACKSON
Insulation 4/14/2022 Approved MORRIS JACKSON
BUILDING-Rough-Frame 4/27/2022 Approved PETER FOLLING
Green Building Rough 4/27/2022 Approved PETER FOLLING
Interior/Exterior Lathing 4/27/2022 Approved PETER FOLLING
Drywall Nailing 5/4/2022 Approved PETER FOLLING
ELECTRICAL-Final 7/29/2022 Not Ready for Inspection PETER FOLLING
Final 7/29/2022 Corrections Issued PETER FOLLING
Gas Test 7/29/2022 Approved PETER FOLLING
Green Building Final 7/29/2022 Approved PETER FOLLING
HVAC-Final 7/29/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Final 7/29/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved PETER FOLLING
Service/Power Release 7/29/2022 Not Ready for Inspection PETER FOLLING
Smoke Detectors 7/29/2022 Approved PETER FOLLING
Final 8/8/2022 OK to Issue CofO PETER FOLLING
Service/Power Release 8/8/2022 Approved PETER FOLLING