15074 W COBALT ST 91342
Certificate Information: 15074 W COBALT ST 91342
- Application / Permit
- 21010-20000-03439
- Plan Check / Job No.
- B21VN08907
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 34' X 35' IRR.-SHAPE 1-STORY ACCESSORY LIVING QUARTERS. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 3/13/2022
- Issuing Office
- Current Status
- CofO Issued on 9/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 7/18/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/13/2022 | GURUNATH NESARAJAH |
| Issued | 3/13/2022 | APPLICANT |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| CofO in Progress | 9/7/2022 | ARAM AVEDISIAN |
| Permit Finaled | 9/12/2022 | MICHAEL SMITH |
| CofO Issued | 9/12/2022 | MICHAEL SMITH |
| Permit Finaled | 9/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/10/2021 | WALTER RAMIREZ |
| ZI | Cleared | 8/10/2021 | PABLO ESTRADA |
| Hydrant and Access approval | Cleared | 10/3/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 1/14/2022 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 3/1/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/2/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 4/14/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 4/22/2022 | Partial Approval | JOHN HAYES |
| Wood Frame | 4/22/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 5/10/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 5/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 5/10/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 5/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 5/10/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 6/8/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 6/8/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 6/8/2022 | Approved | JOHN HAYES |
| Wood Frame | 6/8/2022 | Approved | JOHN HAYES |
| Insulation | 6/14/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/14/2022 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 6/14/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 6/22/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/22/2022 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/15/2022 | Approved | MATTHEW NELSON |
| Final | 8/15/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/15/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/15/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 8/15/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 8/15/2022 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 8/15/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 9/7/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/7/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 9/7/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 9/7/2022 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 9/7/2022 | Approved | ARAM AVEDISIAN |