4177 N BAKMAN AVE 91602
Certificate Information: 4177 N BAKMAN AVE 91602
- Application / Permit
- 21010-20000-03431
- Plan Check / Job No.
- B21VN08894
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (50'-8"x 38'-0") 2-STORY SINGLE FAMILY DWELLING WITH ATT 2-CAR GARAGE WITH (8'x 34'-5") OPEN PATIO TRELLIS, WITH NFPA-13D AUTOMATIC FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/30/2022
- Issuing Office
- Current Status
- CofO Issued on 8/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | TROY DEGUZMAN |
| Corrections Issued | 8/1/2021 | TROY DEGUZMAN |
| Quality Review Completed | 8/3/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/6/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 12/13/2021 | TROY DEGUZMAN |
| Plan Check Approved | 2/8/2022 | TROY DEGUZMAN |
| Plan Check Approved | 3/10/2022 | TROY DEGUZMAN |
| Issued | 3/30/2022 | APPLICANT |
| Refund in Progress | 1/29/2024 | SELENIA GARCIA |
| Refund Closed | 1/29/2024 | SELENIA GARCIA |
| Issued | 1/29/2024 | SELENIA GARCIA |
| CofO in Progress | 8/5/2024 | CHRISTOPHER ROJAS |
| CofO Issued | 8/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2021 | GABRIEL ROBLES |
| Permit | Cleared | 8/19/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/1/2021 | CARLOS AGUILERA |
| ZI | Cleared | 11/5/2021 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 12/28/2021 | JONATAN VELASQUEZ |
| Trees in Parkway | Cleared | 12/28/2021 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 1/4/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/29/2022 | RUEL COLE |
| Green Code | Cleared | 2/1/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/11/2022 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 6/1/2022 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 6/14/2022 | Not Ready for Inspection | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 6/17/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/23/2022 | Partial Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 8/17/2022 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 9/29/2022 | Corrections Issued | CLAYTON GRAHAM |
| Wood Frame | 10/11/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 12/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 12/27/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2023 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 2/10/2023 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 3/7/2023 | Corrections Issued | JACK KARGODORIAN |
| Light Gage Steel Frame | 3/7/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Structural Steel Frame | 3/20/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/4/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 4/10/2023 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/11/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/11/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 4/11/2023 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 4/11/2023 | Partial Approval | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 4/11/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 4/11/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/12/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/14/2023 | Corrections Issued | JACK KARGODORIAN |
| Wood Frame | 4/14/2023 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/21/2023 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 5/22/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 5/30/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/6/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/9/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 8/9/2023 | Approved | JACK KARGODORIAN |
| Pre-Inspection | 12/14/2023 | Partial Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/15/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 5/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/15/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 5/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 5/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/15/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 5/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/15/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/22/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 5/22/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 5/22/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 5/22/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 5/22/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 6/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 6/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 6/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 6/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 6/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 7/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 7/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 7/23/2024 | Approved | JUAN VALENZUELA |
| Final | 8/5/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |