9616 N ODESSA AVE 91343

Certificate Information: 9616 N ODESSA AVE 91343

Application / Permit
21010-20000-03430
Plan Check / Job No.
B21VN08892
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY (26'-6"x25'-6"), 1162 SQFT DETACHED ADU AND 26.65 SQFT ENTRY PORCH PER LAMC 12.22.A.33 (c)(d)
Permit Issued
Issued on 11/5/2021
Issuing Office
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 PETER MOSESIAN
Corrections Issued 8/19/2021 PETER MOSESIAN
Quality Review Completed 8/31/2021 OMID HEDAYAT
Plan Check Approved 11/5/2021 PETER MOSESIAN
Issued 11/5/2021 APPLICANT
CofO in Progress 3/23/2023 RAUL OLAGI
CofO Issued 4/6/2023 MICHAEL SMITH
Permit Finaled 4/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/8/2021 GABRIEL ROBLES
Sewer availability Cleared 9/9/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/10/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 9/16/2021 TIMOTHY POWELL
Hydrant and Access approval Cleared 10/2/2021 MATTHEW CRAIG
Construction near power lines Cleared 10/16/2021 RIDWAN HARDY
Low Impact Development Cleared 10/19/2021 TA ANH
Roof/Waste drainage to street Cleared 10/20/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John Marshall; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2022 Corrections Issued RAUL OLAGI
Sewer 2/28/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/4/2022 Corrections Issued RAUL OLAGI
Sewer 3/4/2022 Approved RAUL OLAGI
PLUMBING-Rough 3/9/2022 Partial Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/22/2022 Approved ROBERT GOLD
Footing/Foundation/Slab 3/22/2022 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Corrections Issued RAUL OLAGI
Green Building Rough 4/1/2022 Not Ready for Inspection RAUL OLAGI
Verify Sprinkler Sign Off 4/1/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Corrections Issued DEANDRE HOFFMAN
BUILDING-Rough-Frame 8/10/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Corrections Issued RAUL OLAGI
Green Building Rough 8/10/2022 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 8/10/2022 Not Ready for Inspection RAUL OLAGI
Verify Sprinkler Sign Off 8/10/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 9/9/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 9/9/2022 Corrections Issued RAUL OLAGI
HVAC-Rough 9/9/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 9/9/2022 Approved RAUL OLAGI
Underground Mechanical 9/9/2022 Partial Approval RAUL OLAGI
Verify Sprinkler Sign Off 9/9/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 9/16/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 9/16/2022 Approved RAUL OLAGI
Green Building Rough 9/16/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 9/16/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 9/16/2022 Not Ready for Inspection RAUL OLAGI
Green Building Rough 10/5/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 10/5/2022 Partial Approval RAUL OLAGI
Insulation 10/14/2022 Approved RAUL OLAGI
Drywall Nailing 10/26/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/18/2022 Approved RAUL OLAGI
ELECTRICAL-Final 2/24/2023 Corrections Issued RAUL OLAGI
Final 2/24/2023 Corrections Issued RAUL OLAGI
Green Building Final 2/24/2023 Approved RAUL OLAGI
HVAC-Final 2/24/2023 Approved RAUL OLAGI
PLUMBING-Final 2/24/2023 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Not Ready RAUL OLAGI
Service/Power Release 2/24/2023 Not Ready for Inspection RAUL OLAGI
Smoke Detectors 2/24/2023 Approved RAUL OLAGI
ELECTRICAL-Final 3/15/2023 Approved RAUL OLAGI
Final 3/15/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 3/15/2023 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/15/2023 SGSOV Approved RAUL OLAGI
Service/Power Release 3/15/2023 Partial Inspection RAUL OLAGI
Final 3/21/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 3/21/2023 Corrections Issued RAUL OLAGI
Final 3/23/2023 OK to Issue CofO RAUL OLAGI
PLUMBING-Final 3/23/2023 Approved RAUL OLAGI
Service/Power Release 3/23/2023 Approved RAUL OLAGI