9616 N ODESSA AVE 91343
Certificate Information: 9616 N ODESSA AVE 91343
- Application / Permit
- 21010-20000-03430
- Plan Check / Job No.
- B21VN08892
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY (26'-6"x25'-6"), 1162 SQFT DETACHED ADU AND 26.65 SQFT ENTRY PORCH PER LAMC 12.22.A.33 (c)(d)
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofO Issued on 4/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | PETER MOSESIAN |
| Corrections Issued | 8/19/2021 | PETER MOSESIAN |
| Quality Review Completed | 8/31/2021 | OMID HEDAYAT |
| Plan Check Approved | 11/5/2021 | PETER MOSESIAN |
| Issued | 11/5/2021 | APPLICANT |
| CofO in Progress | 3/23/2023 | RAUL OLAGI |
| CofO Issued | 4/6/2023 | MICHAEL SMITH |
| Permit Finaled | 4/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/9/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2021 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 9/16/2021 | TIMOTHY POWELL |
| Hydrant and Access approval | Cleared | 10/2/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 10/16/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/19/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 10/20/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John Marshall; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/28/2022 | Corrections Issued | RAUL OLAGI |
| Sewer | 2/28/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/4/2022 | Corrections Issued | RAUL OLAGI |
| Sewer | 3/4/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 3/9/2022 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Approved | ROBERT GOLD |
| Footing/Foundation/Slab | 3/22/2022 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | RAUL OLAGI |
| Verify Sprinkler Sign Off | 4/1/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2022 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Corrections Issued | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 8/10/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 8/10/2022 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 8/10/2022 | Not Ready for Inspection | RAUL OLAGI |
| Verify Sprinkler Sign Off | 8/10/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/9/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 9/9/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 9/9/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 9/9/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 9/9/2022 | Partial Approval | RAUL OLAGI |
| Verify Sprinkler Sign Off | 9/9/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/16/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 9/16/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 9/16/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 9/16/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/16/2022 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 10/5/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 10/5/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 10/14/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 10/26/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/18/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 2/24/2023 | Corrections Issued | RAUL OLAGI |
| Final | 2/24/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/24/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 2/24/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/24/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Not Ready | RAUL OLAGI |
| Service/Power Release | 2/24/2023 | Not Ready for Inspection | RAUL OLAGI |
| Smoke Detectors | 2/24/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 3/15/2023 | Approved | RAUL OLAGI |
| Final | 3/15/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 3/15/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 3/15/2023 | Partial Inspection | RAUL OLAGI |
| Final | 3/21/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 3/21/2023 | Corrections Issued | RAUL OLAGI |
| Final | 3/23/2023 | OK to Issue CofO | RAUL OLAGI |
| PLUMBING-Final | 3/23/2023 | Approved | RAUL OLAGI |
| Service/Power Release | 3/23/2023 | Approved | RAUL OLAGI |